2250 S MALCOLM AVE 90064

Certificate Information: 2250 S MALCOLM AVE 90064

Application / Permit
22014-20000-05278
Plan Check / Job No.
B22VN15916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 50 SQ-FT TO SFD
Permit Issued
Issued on 12/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 11/1/2022 SERGIO MUNIZ
Corrections Issued 11/1/2022 SERGIO MUNIZ
Building Plans Picked Up 11/2/2022 APPLICANT
Plan Check Approved 11/30/2022 MOHAMMAD ESMAILI
Issued 12/6/2022 APPLICANT
CofO in Progress 3/14/2023 ASHLEY THOMPSON
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/7/2022 WESTON PRINGLE
Eng Process Fee Ord 176,300 Cleared 11/17/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 11/17/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 11/22/2022 KIRK LINKLATER

Contact Information

Contractor Addition Building & Design Inc; Lic. No.: 925471-B 4335 VAN NUYS BLVD STE 354      SHERMAN OAKS, CA 91403
Engineer Lu,, Ining; Lic. No.: S3042 47 E LAS FLORES AVENUE      ARCADIA, CA 91006

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 12/14/2022 Not Ready for Inspection ASHLEY THOMPSON
Footing/Foundation/Slab 12/21/2022 Partial Approval ASHLEY THOMPSON
METHANE-Barrier 12/21/2022 Approved ASHLEY THOMPSON
METHANE-Subgrade 12/21/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 1/6/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 1/6/2023 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 1/6/2023 Approved JOHNNY MIRANDA
Insulation 1/13/2023 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 1/23/2023 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/6/2023 Approved JOHNNY MIRANDA
Final 3/6/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 3/6/2023 Approved JOHNNY MIRANDA
Green Building Final 3/6/2023 Approved JOHNNY MIRANDA
Green Building Rough 3/6/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 3/6/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/13/2023 Approved ASHLEY THOMPSON
Final 3/13/2023 Conditional Approval ASHLEY THOMPSON
HVAC-Final 3/13/2023 Approved ASHLEY THOMPSON
PLUMBING-Final 3/13/2023 Approved ASHLEY THOMPSON