2250 S MALCOLM AVE 90064
Certificate Information: 2250 S MALCOLM AVE 90064
- Application / Permit
- 22014-20000-05278
- Plan Check / Job No.
- B22VN15916
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 50 SQ-FT TO SFD
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2022 | SERGIO MUNIZ |
| Corrections Issued | 11/1/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 11/2/2022 | APPLICANT |
| Plan Check Approved | 11/30/2022 | MOHAMMAD ESMAILI |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | ASHLEY THOMPSON |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
| CofO Issued | 3/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/7/2022 | WESTON PRINGLE |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 11/17/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/22/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
| Engineer | Lu,, Ining; Lic. No.: S3042 | 47 E LAS FLORES AVENUE ARCADIA, CA 91006 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Elec/Plmb/HVAC | 12/14/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/21/2022 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Barrier | 12/21/2022 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 12/21/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/6/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 1/6/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 1/6/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 1/13/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 1/23/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | JOHNNY MIRANDA |
| Final | 3/6/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/6/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 3/6/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/6/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/6/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/13/2023 | Approved | ASHLEY THOMPSON |
| Final | 3/13/2023 | Conditional Approval | ASHLEY THOMPSON |
| HVAC-Final | 3/13/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 3/13/2023 | Approved | ASHLEY THOMPSON |