6220 N SIMPSON AVE 91606

Certificate Information: 6220 N SIMPSON AVE 91606

Application / Permit
22014-20000-05256
Plan Check / Job No.
B22VN15827
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: (N) 16'0" X 23'0" ADDITION TO CREATE (N) BEDROOM AND (N) BATHROOM & REMODEL TO (E) SFD PER ENGINEER.
Permit Issued
Issued on 8/8/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2022 APPLICANT
Assigned to Plan Check Engineer 11/1/2022 ALEC MOUSAKHANIAN
Corrections Issued 11/2/2022 ALEC MOUSAKHANIAN
Applicant returned to address corrections 4/10/2023 PINANK PATEL
Applicant returned to address corrections 6/29/2023 PINANK PATEL
Applicant returned to address corrections 7/19/2023 ISIS ARGUETA
Applicant returned to address corrections 7/28/2023 ISIS ARGUETA
Plan Check Approved 8/1/2023 ALEC MOUSAKHANIAN
Issued 8/8/2023 APPLICANT
CofO in Progress 12/30/2023 RYAN SALAZAR
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/3/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 11/9/2022 ROMAN GUTIERREZ
Sewer availability Cleared 3/31/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/17/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/18/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 8/25/2023 Approved JOHN HAYES
Special/Order Compliance 8/25/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 8/31/2023 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 8/31/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/8/2023 Partial Approval JOHN HAYES
Insulation 9/8/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/8/2023 Partial Approval JOHN HAYES
Insulation 9/13/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 10/16/2023 Not Ready for Inspection JOHN HAYES
Shower Pan 10/20/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 10/25/2023 Approved RYAN SALAZAR
Shower Pan 10/25/2023 Approved RYAN SALAZAR
Insulation 10/31/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/31/2023 Approved KEVIN BERBERYAN
Drywall Nailing 11/14/2023 Approved JOHN HAYES
Final 12/26/2023 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 12/26/2023 Approved JOHN HAYES
Final 12/29/2023 OK to Issue CofO RYAN SALAZAR