7524 N SYLVIA AVE 91335
Certificate Information: 7524 N SYLVIA AVE 91335
- Application / Permit
- 22014-20000-05253
- Plan Check / Job No.
- B22VN15821
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert garage to ADU with addition.
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Current Status
- CofO Issued on 2/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2022 | JOE VO |
| Corrections Issued | 11/1/2022 | JOE VO |
| Plan Check Approved | 1/3/2023 | JOE VO |
| Issued | 1/31/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | JEFFREY BULL |
| Permit Finaled | 2/16/2024 | JOHN JANSON |
| Permit Finaled | 2/16/2024 | JOHN JANSON |
| CofO Issued | 2/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/3/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 12/13/2022 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/21/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Approved | DAVID SANDOVAL |
| Sewer | 4/10/2023 | Approved | MORRIS JACKSON |
| Underground Mechanical | 4/10/2023 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 4/17/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 6/14/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 6/14/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 6/14/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 6/14/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 6/29/2023 | Partial Approval | JEFFREY BULL |
| Shower Pan | 6/29/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/1/2023 | Approved | JEFFREY BULL |
| Gas Test | 8/1/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/1/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 8/1/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | JEFFREY BULL |
| Final | 10/27/2023 | Corrections Issued | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 10/27/2023 | Approved | JEFFREY BULL |
| Final | 2/8/2024 | OK to Issue CofO | JEFFREY BULL |