5644 N CRANER AVE 91601

Certificate Information: 5644 N CRANER AVE 91601

Application / Permit
22014-20000-05241
Plan Check / Job No.
B22VN15790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION & COVERT PORTION OF GARAGE TO MAKE A 20'0"X29'0" 2-STORY ACCESSORY DWELLING UNIT WITH A 20'0"X13'0" 1-CAR GARAGE PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/24/2023
Issuing Office
Current Status
CofO Issued on 12/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 MARVEL DELACRUZ
Corrections Issued 11/17/2022 MARVEL DELACRUZ
Quality Review Completed 11/18/2022 OMID HEDAYAT
Building Plans Picked Up 12/2/2022 APPLICANT
Plan Check Approved 4/24/2023 MARVEL DELACRUZ
Issued 4/24/2023 APPLICANT
CofO in Progress 11/18/2025 JOSE AVILA
Permit Finaled 12/19/2025 RUBEN SALAS
CofO Issued 12/19/2025 RUBEN SALAS
Permit Finaled 12/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/17/2023 SHAELYN ROWEN
Eng Process Fee Ord 176,300 Cleared 2/17/2023 SHAELYN ROWEN
Sewer availability Cleared 2/17/2023 SHAELYN ROWEN
Hydrant and Access approval Cleared 3/11/2023 KURT CORRAL
Low Impact Development Cleared 3/13/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/13/2023 CARLOS AGUILERA
Green Code Cleared 4/24/2023 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/22/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 6/22/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/22/2023 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 6/23/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 6/29/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 6/29/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/12/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/12/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/12/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/1/2023 Approved JOHN HAYES
Footing/Foundation/Slab 8/1/2023 Approved JOHN HAYES
Underground Mechanical 8/1/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Partial Approval JOHN HAYES
Wood Frame 8/29/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 2/29/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 3/1/2024 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Approved DAVID ANDERSON
Green Building Rough 3/1/2024 Not Ready for Inspection DAVID ANDERSON
Wood Frame 3/1/2024 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 3/26/2024 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 4/1/2024 Corrections Issued SALVADOR MARTINEZ
Gas Test 4/1/2024 Partial Inspection SALVADOR MARTINEZ
PLUMBING-Rough 4/1/2024 Corrections Issued SALVADOR MARTINEZ
Wood Frame 4/1/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 4/4/2024 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/8/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 7/30/2024 Corrections Issued MICHAEL CORTEZ
Insulation 8/12/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/12/2024 Approved SALVADOR MARTINEZ
Insulation 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Sewer 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 12/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 11/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 11/5/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/17/2025 OK to Issue CofO JOSE AVILA