10191 W ELKWOOD ST 91352

Certificate Information: 10191 W ELKWOOD ST 91352

Application / Permit
22014-20000-05231
Plan Check / Job No.
B22VN15763
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION (43' x 35')TO (E)SFD AND PARTIAL RE-FRAMING OF (E) ROOF *See comments*
Permit Issued
Issued on 1/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 RAMA DABADGE
Corrections Issued 10/31/2022 RAMA DABADGE
Building Plans Picked Up 11/2/2022 APPLICANT
Applicant returned to address corrections 12/23/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 1/10/2023 ISIS ARGUETA
Applicant returned to address corrections 1/20/2023 JESSE ARELLANO
Plan Check Approved 1/27/2023 ISIS ARGUETA
Issued 1/27/2023 APPLICANT
CofO in Progress 10/25/2023 DAVID ANDERSON
Permit Finaled 12/12/2023 RUBEN SALAS
CofO Issued 12/12/2023 RUBEN SALAS
Permit Finaled 12/12/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/11/2023 MEGAN GODINEZ
Low Impact Development Cleared 1/18/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/19/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 1/19/2023 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 1/19/2023 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 1/19/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2023 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 3/10/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/14/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 6/8/2023 Corrections Issued DAVID ANDERSON
Green Building Rough 6/8/2023 Corrections Issued DAVID ANDERSON
Rough-Elec/Plmb/HVAC 6/8/2023 Corrections Issued DAVID ANDERSON
Deputy Drilled-In Anchors 6/22/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Approved DAVID ANDERSON
Green Building Rough 7/5/2023 Approved DAVID ANDERSON
MERV13>=Rough 7/5/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/10/2023 Partial Approval DAVID ANDERSON
Insulation 8/17/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/21/2023 Approved DAVID ANDERSON
Drywall Nailing 8/25/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 9/29/2023 Approved DAVID ANDERSON
Final 9/29/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 9/29/2023 Approved DAVID ANDERSON
Green Building Final 9/29/2023 Approved DAVID ANDERSON
MERV13>=Final 9/29/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 9/29/2023 Approved DAVID ANDERSON
Final 10/24/2023 OK to Issue CofO DAVID ANDERSON