9238-9240 N SOPHIA AVE 91343

Certificate Information: 9238-9240 N SOPHIA AVE 91343

Application / Permit
22014-20000-05228
Plan Check / Job No.
B22VN15752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SFD TO ADU WITH AN ADDITION PER ATTACHED ADU ORDINANCE
Permit Issued
Issued on 3/15/2023
Issuing Office
Current Status
CofO Issued on 5/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 CARLOS MONTES
Corrections Issued 11/12/2022 CARLOS MONTES
Quality Review Completed 11/14/2022 GARO TELMI
Plan Check Approved 3/3/2023 CARLOS MONTES
Issued 3/15/2023 SHANNON HAAS
CofO in Progress 3/29/2024 RAUL OLAGI
Permit Finaled 5/3/2024 RUBEN SALAS
Permit Finaled 5/3/2024 RUBEN SALAS
CofO Issued 5/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/2/2023 MATTHEW MAHLEBASHIAN
Eng Process Fee Ord 176,300 Cleared 2/2/2023 MATTHEW MAHLEBASHIAN
GPI Written Notices Cleared 2/2/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 2/2/2023 CARLOS MONTES
Low Impact Development Cleared 2/6/2023 ROGELIO CORTES
Sewer availability Cleared 2/9/2023 MATTHEW MAHLEBASHIAN
Construction near power lines Cleared 2/11/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/17/2023 MATTHEW MAHLEBASHIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/16/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/22/2023 Partial Approval RAUL OLAGI
Underground Mechanical 6/22/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 7/7/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 9/7/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 9/7/2023 Not Ready for Inspection RAUL OLAGI
Insulation 9/7/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/7/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 9/22/2023 Approved RAUL OLAGI
HVAC-Rough 9/22/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/22/2023 Approved RAUL OLAGI
Deputy Wood Construction 9/27/2023 Conditional Approval JUAN VALENZUELA
HVAC-Rough 10/6/2023 Approved MICHEL ABAJAN
Sewer 10/6/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/10/2023 Approved RAUL OLAGI
Green Building Rough 10/10/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 10/10/2023 Approved RAUL OLAGI
Drywall Nailing 10/24/2023 Corrections Issued RAUL OLAGI
Insulation 10/24/2023 Corrections Issued RAUL OLAGI
Shower Pan 10/24/2023 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 11/2/2023 Partial Approval RAUL OLAGI
Insulation 11/2/2023 Partial Approval RAUL OLAGI
Shower Pan 11/2/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 11/27/2023 Approved RAUL OLAGI
Shower Pan 11/27/2023 Approved RAUL OLAGI
Insulation 12/21/2023 Approved RAUL OLAGI
Final 3/22/2024 Corrections Issued RAUL OLAGI
Green Building Final 3/22/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 3/22/2024 Approved RAUL OLAGI
Final 3/29/2024 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved RAUL OLAGI