15543 W VALERIO ST 91406
Certificate Information: 15543 W VALERIO ST 91406
- Application / Permit
- 22014-20000-05227
- Plan Check / Job No.
- B22VN15750
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: One story additions to single family dwelling. Interior remodel throughout house with door and window change outs. Replace roof . Trellis addition.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Current Status
- Issued on 2/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2022 | RICARDO RAMIREZ |
| Corrections Issued | 10/31/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 2/20/2023 | RICARDO RAMIREZ |
| Issued | 2/21/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 11/9/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 2/16/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/17/2023 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 4/26/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/24/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/8/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/8/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/18/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/29/2024 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/2/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/7/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/13/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 2/13/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 2/13/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/11/2024 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 4/11/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 4/30/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | KIRK SANDERS |
| Shower Pan | 4/30/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 5/24/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 5/24/2024 | Approved | JOHN COLEMAN |