5109 N BILOXI AVE 91601

Certificate Information: 5109 N BILOXI AVE 91601

Application / Permit
22014-20000-05183
Plan Check / Job No.
B22VN15646
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL INCLUDING RELOCATING THE KITCHEN AND REMOVE/REPLACE LIVING ROOM CEILING AND WALLS, W/(20'-5"x38'-0"), 795 SQFT GROUND FLOOR ADDITION TO SFD AND WITH NEW 156 SQFT COVERED PORCH.
Permit Issued
Issued on 5/16/2023
Issuing Office
Valley
Current Status
Issued on 5/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 PETER MOSESIAN
Corrections Issued 11/9/2022 PETER MOSESIAN
Quality Review Completed 11/15/2022 OMID HEDAYAT
Building Plans Picked Up 11/18/2022 APPLICANT
Plan Check Approved 5/3/2023 PETER MOSESIAN
Issued 5/16/2023 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 4/21/2023 ORVAL HERNANDEZ-MARCI
Sewer availability Cleared 4/28/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/2/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 5/2/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/23/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 8/23/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 8/23/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 9/21/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 9/21/2023 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 3/21/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/29/2024 Corrections Issued JENNIFER RABUCHIN
Deputy Reinf. Concrete 8/15/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/19/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/19/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/19/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/27/2024 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 8/27/2024 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Partial Approval DAVID MATSON
Green Building Rough 8/27/2024 Not Ready for Inspection DAVID MATSON
Insulation 8/27/2024 Partial Approval DAVID MATSON
ELECTRICAL-Rough 2/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/5/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/3/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 7/7/2025 Approved ROBERTO PALACIOS-LOPEZ