13962 W AZTEC ST 91342
Certificate Information: 13962 W AZTEC ST 91342
- Application / Permit
- 22014-20000-05179
- Plan Check / Job No.
- B22VN15640
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-4" X 17'-7" ADDITION TO AND CONVERT (E) DETACHED 18'-0" X 18'-0" GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - ALL WORK PER WFPP
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 11/6/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/14/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 11/16/2022 | DANIEL ABRAMYAN |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 11/22/2023 | KEVIN BERBERYAN |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
| CofO Issued | 2/14/2024 | RUBEN SALAS |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/10/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/12/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/17/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/11/2023 | Partial Approval | JOHN COLEMAN |
| Green Building Rough | 5/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/25/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/25/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 5/31/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 5/31/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Sewer | 5/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 6/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 6/27/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 7/3/2023 | Approved | MICHEL ABAJAN |
| Insulation | 7/3/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/14/2023 | Approved | MICHEL ABAJAN |
| Gas Test | 7/14/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/31/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/31/2023 | Approved | MICHEL ABAJAN |
| Final | 9/20/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/20/2023 | Approved | KEVIN BERBERYAN |
| Final | 9/29/2023 | Conditional Approval | KEVIN BERBERYAN |
| Final | 11/22/2023 | OK to Issue CofO | KEVIN BERBERYAN |