14283 W AZTEC ST 91342

Certificate Information: 14283 W AZTEC ST 91342

Application / Permit
22014-20000-05169
Plan Check / Job No.
B22VN15622
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-0" X 16'-0" ADDITION TO AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP & ENGINEERING DETAILS.
Permit Issued
Issued on 2/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/21/2022 ARTIN ZARUKIAN
Corrections Issued 10/22/2022 ARTIN ZARUKIAN
Building Plans Picked Up 10/24/2022 APPLICANT
Plan Check Approved 2/8/2023 ISIS ARGUETA
Issued 2/9/2023 APPLICANT
CofO in Progress 10/29/2024 MISAEL ESPARZA
CofO Issued 11/13/2024 DANIEL ORRANTE
Permit Finaled 11/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/27/2022 RYAN KIM
Roof/Waste drainage to street Cleared 10/27/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 10/31/2022 RYAN KIM
Sewer availability Cleared 10/31/2022 RYAN KIM
Construction near power lines Cleared 1/12/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/24/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/26/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 10/26/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 10/26/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/30/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 11/16/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/27/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved JENNIFER RABUCHIN
Green Building Rough 11/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/27/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/27/2023 Approved JENNIFER RABUCHIN
Insulation 12/6/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/6/2023 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 12/11/2023 Approved JENNIFER RABUCHIN
Green Building Rough 12/11/2023 Approved JENNIFER RABUCHIN
Insulation 12/11/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/11/2023 Approved JENNIFER RABUCHIN
Shower Pan 12/11/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/16/2024 Corrections Issued JENNIFER RABUCHIN
Final 9/16/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/16/2024 Approved JENNIFER RABUCHIN
Green Building Final 9/16/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 9/16/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/16/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/16/2024 Approved JENNIFER RABUCHIN
Final 9/23/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 9/23/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Approved MISAEL ESPARZA
Final 10/29/2024 OK to Issue CofO MISAEL ESPARZA