ADD 20'-4" x 8'-6" TO SINGLE FAMILY DWELLING FOR DEN EXTENSION. CONVERT BDRM TO STUDY.- ALL WORK PER ENGINEER
Permit Issued
Issued on 11/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/18/2022 DANIEL ABRAMYAN
Corrections Issued 10/18/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 11/18/2022 ANTOAN MISHRIKI
Plan Check Approved 11/28/2022 ANGELICA MARTINEZ
Issued 11/29/2022 APPLICANT
CofO in Progress 2/24/2023 JENNIFER RABUCHIN
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/18/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 10/26/2022 VASIL MIHALEV

Contact Information

Contractor E N B Construction Inc; Lic. No.: 990795-B 15115 PARTHENIA ST APT #232      NORTH HILLS, CA 91343
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/15/2022 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 12/15/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/21/2022 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 12/23/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/18/2023 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 1/18/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Partial Approval ARAM AVEDISIAN
Green Building Rough 1/18/2023 Not Ready for Inspection ARAM AVEDISIAN
Deputy Wood Construction 1/23/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 1/25/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved JENNIFER RABUCHIN
Green Building Rough 1/25/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 1/31/2023 Approved JENNIFER RABUCHIN
Insulation 2/1/2023 Approved JOHN COLEMAN
Drywall Nailing 2/6/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/23/2023 Approved JENNIFER RABUCHIN
Final 2/23/2023 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 2/23/2023 Approved JENNIFER RABUCHIN
Green Building Final 2/23/2023 Approved JENNIFER RABUCHIN
Green Building Rough 2/23/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Approved JENNIFER RABUCHIN