13502 W BROMWICH ST 91331
Certificate Information: 13502 W BROMWICH ST 91331
- Application / Permit
- 22014-20000-05128
- Plan Check / Job No.
- B22VN15477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Convert (e) garage and addition to ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | KHUONG TRUONG |
| Corrections Issued | 11/26/2022 | KHUONG TRUONG |
| Plan Check Approved | 6/12/2023 | JOSEPH RAFOLS |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 2/23/2024 | GREGG CUMMINGS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2023 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 2/14/2023 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 3/6/2023 | CHRIS CHAHBAZ |
| Construction near power lines | Cleared | 4/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 8/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 8/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/8/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 8/8/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 8/8/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/11/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 9/11/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/11/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 9/11/2023 | Approved | GREGG CUMMINGS |
| Sewer | 9/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/28/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 9/28/2023 | Approved | GREGG CUMMINGS |
| Insulation | 10/3/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/12/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/12/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/19/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 10/19/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 10/19/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/13/2023 | No Access for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 12/15/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 1/11/2024 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 1/11/2024 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/11/2024 | No Access for Inspection | GREGG CUMMINGS |
| Final | 1/16/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/16/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/16/2024 | Approved | GREGG CUMMINGS |
| Final | 1/25/2024 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | GREGG CUMMINGS |
| Final | 1/26/2024 | Corrections Issued | GREGG CUMMINGS |
| Final | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/1/2024 | Approved | GREGG CUMMINGS |
| Final | 2/1/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/1/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/1/2024 | Approved | GREGG CUMMINGS |