11345 W DELANO ST 91606
Certificate Information: 11345 W DELANO ST 91606
- Application / Permit
- 22014-20000-05091
- Plan Check / Job No.
- B22VN15373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & MAJOR REMODEL TO (E) 1-STORY SFD [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/8/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/24/2023 | STEVEN KIM |
| Applicant returned to address corrections | 2/24/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/2/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/7/2023 | NILOOFAR MEHRAIN |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 9/26/2023 | JOHN HAYES |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/13/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 2/3/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/28/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/5/2023 | Not Ready for Inspection | JOHN HAYES |
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/14/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/18/2023 | Partial Approval | JOHN COLEMAN |
| Green Building Rough | 4/18/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Deputy Wood Construction | 5/3/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 5/16/2023 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 5/16/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/16/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/16/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/16/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/16/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/23/2023 | Approved | JOHN HAYES |
| Gas Test | 5/23/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 5/23/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/23/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 5/23/2023 | Approved | JOHN HAYES |
| Insulation | 5/25/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/1/2023 | Approved | JOHN HAYES |
| Shower Pan | 6/1/2023 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 6/2/2023 | Approved | JOHN HAYES |
| Shower Pan | 6/2/2023 | Approved | JOHN HAYES |
| Shower Pan | 6/9/2023 | Corrections Issued | JOHN HAYES |
| Shower Pan | 6/15/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 7/25/2023 | Approved | JOHN HAYES |
| Final | 7/25/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 7/25/2023 | Approved | JOHN HAYES |
| HVAC-Final | 7/25/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 7/25/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 7/25/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 9/11/2023 | Approved | JOHN HAYES |
| Final | 9/11/2023 | OK to Issue CofO | JOHN HAYES |
| HVAC-Final | 9/11/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 9/11/2023 | Approved | JOHN HAYES |
| Service/Power Release | 9/11/2023 | Approved | JOHN HAYES |