13551 W EBELL ST 91402
Certificate Information: 13551 W EBELL ST 91402
- Application / Permit
- 22014-20000-05089
- Plan Check / Job No.
- B22VN15372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-5" X 20'-5" DETACHED GARAGE AND ADD 20'-5" X 28'-5" 2ND FLOOR TO CREATE A (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | RAPHAEL ROSAS |
| Corrections Issued | 11/9/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/15/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 2/17/2023 | RAPHAEL ROSAS |
| Issued | 4/25/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | GREGG CUMMINGS |
| Permit Finaled | 6/24/2024 | RUBEN SALAS |
| CofO Issued | 6/24/2024 | RUBEN SALAS |
| Permit Finaled | 6/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/28/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/28/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 1/24/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/15/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/16/2023 | JOHN LIN |
Contact Information
| Contractor | G S Tingling; Lic. No.: 952884-B | 154-25 SHERMAN WAY #226 VAN NUYS, CA 91406 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 5/2/2023 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 5/2/2023 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/11/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/11/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 5/11/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/12/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 7/13/2023 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 7/14/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 8/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/6/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/6/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/17/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/22/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 12/15/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/28/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 12/28/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/10/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/29/2024 | Partial Approval | CRAIG DAVIS |
| Insulation | 2/2/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 2/9/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/7/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 3/11/2024 | Approved | MATTHEW NELSON |
| Final | 5/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 5/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 5/7/2024 | Approved | GREGG CUMMINGS |
| Final | 5/23/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/23/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Final | 6/4/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/4/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | VINCENT HANLEY |
| Final | 6/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/11/2024 | Approved | GREGG CUMMINGS |
| Final | 6/11/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 6/11/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 6/11/2024 | Approved | GREGG CUMMINGS |