6044 N CARTWRIGHT AVE 91606
Certificate Information: 6044 N CARTWRIGHT AVE 91606
- Application / Permit
- 22014-20000-05077
- Plan Check / Job No.
- B22VN15326
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 23'-6" X 26'-4" IRREGULAR SHAPED 2-STORY ADDITION TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/23/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | RAPHAEL ROSAS |
| Corrections Issued | 11/7/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Applicant returned to address corrections | 2/21/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 2/23/2023 | RAPHAEL ROSAS |
| Issued | 2/23/2023 | APPLICANT |
| CofO in Progress | 12/1/2023 | JOHN HAYES |
| Permit Finaled | 12/29/2023 | RUBEN SALAS |
| CofO Issued | 12/29/2023 | RUBEN SALAS |
| Permit Finaled | 12/29/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/15/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 1/26/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/21/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/24/2023 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/31/2023 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | JOHN HAYES |
| PLUMBING-Rough | 4/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Structural Steel Frame | 4/27/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 6/7/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 8/2/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 8/2/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 8/21/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/21/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/21/2023 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 8/21/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/28/2023 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/28/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 9/14/2023 | Approved | JOHN HAYES |
| Green Building Rough | 9/14/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 9/14/2023 | Approved | JOHN HAYES |
| Shower Pan | 9/14/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/27/2023 | Approved | JACK KARGODORIAN |
| Insulation | 10/5/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 10/12/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/13/2023 | No Access for Inspection | JOHN HAYES |
| HVAC-Rough | 11/13/2023 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/13/2023 | No Access for Inspection | JOHN HAYES |
| Final | 11/14/2023 | Corrections Issued | JOHN HAYES |
| Final | 11/21/2023 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Final | 11/21/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 11/21/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 11/21/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 11/21/2023 | Approved | KEVIN BERBERYAN |
| Final | 11/30/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |