8457 N RINCON AVE 91352
Certificate Information: 8457 N RINCON AVE 91352
- Application / Permit
- 22014-20000-05074
- Plan Check / Job No.
- B22VN15322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Addition at rear of (E) 1-story S.F.D. all work per WFPP
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2022 | MINA HABILI |
| Corrections Issued | 10/25/2022 | MINA HABILI |
| Applicant returned to address corrections | 5/3/2023 | MINA HABILI |
| Plan Check Approved | 5/11/2023 | MINA HABILI |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 12/12/2023 | MATTHEW NELSON |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/25/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2022 | RYAN KIM |
| Sewer availability | Cleared | 11/8/2022 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/25/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 7/28/2023 | Corrections Issued | RAUL OLAGI |
| Sewer | 7/28/2023 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 8/1/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/14/2023 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 8/14/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/14/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/3/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/3/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/3/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/3/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | WILLIAM WREN |
| Insulation | 10/12/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/12/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/26/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/26/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 12/4/2023 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 12/4/2023 | Approved | MATTHEW NELSON |
| Final | 12/12/2023 | OK to Issue CofO | MATTHEW NELSON |