6729 N ORION AVE 91406
Certificate Information: 6729 N ORION AVE 91406
- Application / Permit
- 22014-20000-05069
- Plan Check / Job No.
- B22VN15314
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED ONE CAR GARAGE TO BEDROOM & CLOSET, 10'-4" X 10'-4" ADDITION OF (N) BATHROOM. & ONE CAR CARPORT TO (E) SFD.
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 10/17/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/20/2022 | APPLICANT |
| Applicant returned to address corrections | 11/14/2022 | JESSE ARELLANO |
| Plan Check Approved | 11/18/2022 | ANTOAN MISHRIKI |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | RYAN SALAZAR |
| No Progress | 4/10/2023 | ROBERT GOLD |
| CofO in Progress | 4/21/2023 | ROBERT GOLD |
| CofO in Progress | 1/16/2025 | RYAN SALAZAR |
| Permit Finaled | 3/7/2025 | RUBEN SALAS |
| CofO Issued | 3/7/2025 | RUBEN SALAS |
| Permit Finaled | 3/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 11/3/2022 | FERNANDO GIL |
Contact Information
| Contractor | Pavlovich Construction Co; Lic. No.: 388868-B | 22817 VENTURA BLVD 1001 WOODLAND HILLS, CA 91364 |
| Engineer | Dorier,, David Julien Miche; Lic. No.: C88481 | 950 S GRAND AVE 4TH FLOOR LOS ANGELES, CA 90015 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2022 | Conditional Approval | JOHN COLEMAN |
| Underground Mechanical | 12/22/2022 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| Insulation | 2/1/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/1/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/6/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Approved | JENNIFER RABUCHIN |
| Final | 3/21/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 3/21/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 3/21/2023 | Approved | RYAN SALAZAR |
| MERV13>=Final | 3/21/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 3/21/2023 | Approved | RYAN SALAZAR |
| Final | 3/23/2023 | Conditional Approval | RYAN SALAZAR |
| Special/Order Compliance | 4/11/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 1/17/2025 | OK to Issue CofO | RYAN SALAZAR |