14729 W SYLVAN ST 91411
Certificate Information: 14729 W SYLVAN ST 91411
- Application / Permit
- 22014-20000-05051
- Plan Check / Job No.
- B22VN15255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Existing garage conversion to ADU with addition per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- Issued on 12/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | JASON JANGADA |
| Corrections Issued | 11/4/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/1/2023 | JASON JANGADA |
| Applicant returned to address corrections | 5/4/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 5/11/2023 | EDWIN ESPIN |
| Plan Check Approved | 5/17/2023 | JASON JANGADA |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 10/9/2024 | RYAN SALAZAR |
| CofO in Progress | 12/6/2024 | RYAN SALAZAR |
| No Progress | 12/6/2024 | RYAN SALAZAR |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | CARLOS AGUILERA |
| Tenant Habitability Plan | Cleared | 12/13/2022 | MICHAEL SOTO |
| "Q" conditions | Cleared | 12/16/2022 | DANIEL CORONADO |
| Construction near power lines | Cleared | 3/14/2023 | TINA MIRANDA |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | 525 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2023 | Partial Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 9/13/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/20/2023 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/16/2023 | Conditional Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/5/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/5/2024 | Partial Approval | RYAN SALAZAR |
| Insulation | 2/1/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/7/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/7/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 7/16/2024 | Corrections Issued | RYAN SALAZAR |
| Final | 7/16/2024 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 7/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Final | 9/25/2024 | No Access for Inspection | MICHEL ABAJAN |
| Final | 9/25/2024 | No Access for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 9/25/2024 | No Access for Inspection | MICHEL ABAJAN |
| Final | 10/8/2024 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 10/8/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 10/8/2024 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 12/9/2024 | Corrections Issued | RYAN SALAZAR |