6024-6026 N MORELLA AVE 91606

Certificate Information: 6024-6026 N MORELLA AVE 91606

Application / Permit
22014-20000-05047
Plan Check / Job No.
B22VN15247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION AND CONVERT (E) ATTACHED GARAGE IN 1-STORY SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 3/24/2023
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/18/2022 DANIEL YIP
Corrections Issued 10/19/2022 DANIEL YIP
Applicant returned to address corrections 12/6/2022 DANIEL YIP
Applicant returned to address corrections 12/17/2022 DANIEL YIP
Plan Check Approved 12/30/2022 DANIEL YIP
Issued 3/24/2023 APPLICANT
CofO in Progress 6/5/2024 JOSE AVILA
CofO in Progress 7/2/2024 JUAN VALENZUELA
CofO in Progress 7/2/2024 JOSE AVILA
No Progress 7/2/2024 JOSE AVILA
Permit Finaled 10/30/2024 DANIEL ORRANTE
CofO Issued 10/30/2024 DANIEL ORRANTE
Permit Finaled 10/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/19/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/19/2022 COLIN LOREDO
Sewer availability Cleared 10/19/2022 COLIN LOREDO
Low Impact Development Cleared 12/29/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 12/29/2022 COLIN LOREDO

Contact Information

Contractor Vargas Construction And Design Llc; Lic. No.: 1087723-B       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/6/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/16/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/9/2023 Partial Approval JOHN HAYES
Wood Frame 8/9/2023 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 8/15/2023 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/17/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 8/17/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 9/13/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 10/3/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/24/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/24/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 10/24/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/24/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/17/2023 Corrections Issued ROBERT GOLD
Rough-Elec/Plmb/HVAC 11/17/2023 Corrections Issued ROBERT GOLD
Shower Pan 11/17/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 11/28/2023 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 11/28/2023 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 11/28/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/6/2023 Approved JOHN COLEMAN
ELECTRICAL-Rough 12/6/2023 Approved JOHN COLEMAN
PLUMBING-Rough 12/6/2023 Approved JOHN COLEMAN
Rough-Elec/Plmb/HVAC 12/6/2023 Approved JOHN COLEMAN
Insulation 12/13/2023 Partial Approval JOHN COLEMAN
Drywall Nailing 12/29/2023 Approved RYAN SALAZAR
Final 5/7/2024 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/7/2024 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/7/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/7/2024 Approved JOHN HAYES
Final 5/10/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved JENNIFER RABUCHIN
Final 6/4/2024 OK to Issue CofO JOSE AVILA