18153 W SATICOY ST 91335

Certificate Information: 18153 W SATICOY ST 91335

Application / Permit
22014-20000-05013
Plan Check / Job No.
B22VN15159
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-10 3/4"x 39'-10" (540 sf habitable and 34.3 sf storage) IRREGULAR SHAPED ADDITION TO AN EXISTING SINGLE FAMILY DWELLING PER ENGINEERING. NFPA-13D FIRE SPRINKLERS THRU-OUT.
Permit Issued
Issued on 8/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 MIROOSH KHACHATOORIAN
Corrections Issued 10/13/2022 MIROOSH KHACHATOORIAN
Building Plans Picked Up 10/19/2022 APPLICANT
Plan Check Approved 8/9/2023 OMAR GARNICA
Issued 8/9/2023 APPLICANT
CofO in Progress 10/9/2024 JEFFREY BULL
Permit Finaled 3/12/2025 JOHN JANSON
CofO Issued 3/12/2025 JOHN JANSON
Permit Finaled 3/12/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/4/2022 COLIN LOREDO
Low Impact Development Cleared 3/23/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 5/16/2023 CARLOS AGUILERA

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor G & V Dream Construction Inc; Lic. No.: 1032179-B 6639 BELMAR AVE      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2023 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/12/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 10/12/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved JEFFREY BULL
PLUMBING-Rough 10/24/2023 Partial Approval JEFFREY BULL
Underground Mechanical 10/24/2023 Approved JEFFREY BULL
Wood Frame 10/24/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval JEFFREY BULL
Insulation 10/27/2023 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 1/12/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 1/12/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved JEFFREY BULL
Green Building Rough 1/12/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 1/12/2024 Approved JEFFREY BULL
PLUMBING-Rough 1/12/2024 Approved JEFFREY BULL
Wood Frame 1/12/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/19/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 1/19/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 1/19/2024 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 1/31/2024 Approved JEFFREY BULL
Insulation 1/31/2024 Approved JEFFREY BULL
Drywall Nailing 2/9/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 2/9/2024 Approved JEFFREY BULL
Shower Pan 2/9/2024 Approved JEFFREY BULL
Final 7/29/2024 Corrections Issued JEFFREY BULL
Green Building Final 7/29/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 7/29/2024 Approved JEFFREY BULL
Final 10/9/2024 OK to Issue CofO JEFFREY BULL