6702 N ALLOTT AVE 91401

Certificate Information: 6702 N ALLOTT AVE 91401

Application / Permit
22014-20000-05011
Plan Check / Job No.
B22VN15156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
29'-9" X 32'-0" ACCESSORY DWELLING UNIT ADDITION TO (E) ALQ & STORAGE PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERING.
Permit Issued
Issued on 10/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2022 APPLICANT
Assigned to Plan Check Engineer 10/14/2022 ARTIN ZARUKIAN
Corrections Issued 10/15/2022 ARTIN ZARUKIAN
Building Plans Picked Up 11/16/2022 APPLICANT
Plan Check Approved 9/28/2023 ISIS ARGUETA
Issued 10/3/2023 APPLICANT
CofO in Progress 5/10/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 6/5/2024 RUBEN SALAS
CofO Issued 6/5/2024 RUBEN SALAS
Permit Finaled 6/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/25/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/23/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/24/2023 DAGOVERTO GUERRERO
Low Impact Development Cleared 9/19/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 9/19/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/20/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 10/20/2023 Approved KIRK SANDERS
Underground Mechanical 10/20/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 11/7/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 11/7/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 11/7/2023 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/15/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 11/15/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 11/15/2023 Approved KIRK SANDERS
Green Building Rough 11/15/2023 Approved KIRK SANDERS
HVAC-Rough 11/15/2023 Approved KIRK SANDERS
PLUMBING-Rough 11/15/2023 Approved KIRK SANDERS
Special/Order Compliance 11/17/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/21/2023 Approved JUAN VALENZUELA
Insulation 11/21/2023 Approved JUAN VALENZUELA
Drywall Nailing 11/29/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 2/9/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/21/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/27/2024 Partial Approval JOSE AVILA
HVAC-Final 3/21/2024 Corrections Issued JOSE AVILA
HVAC-Final 3/27/2024 Approved JOSE AVILA
Final 4/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/29/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 5/1/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 5/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/1/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 5/2/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 5/9/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 5/9/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/9/2024 Approved ROBERTO PALACIOS-LOPEZ