5246 N SALE AVE 91364

Certificate Information: 5246 N SALE AVE 91364

Application / Permit
22014-20000-04980
Plan Check / Job No.
B22VN15099
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 42'2" X 27'4" TO AN EXISTING SINGLE FAMILY DWELLING PER ENGINEERING WITH TRELLIS AND REMODEL INTERIOR BATHROOMS, BEDROOM, AND KITCHEN
Permit Issued
Issued on 10/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/11/2022 MADISON ODELL
Corrections Issued 10/12/2022 MADISON ODELL
Building Plans Picked Up 10/18/2022 APPLICANT
Plan Check Approved 10/28/2022 MADISON ODELL
Issued 10/28/2022 APPLICANT
CofO in Progress 5/14/2024 MORRIS JACKSON
CofO in Progress 5/14/2024 MORRIS JACKSON
Permit Finaled 6/18/2024 JOHN JANSON
CofO Issued 6/18/2024 JOHN JANSON
Permit Finaled 6/18/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/20/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 10/20/2022 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2023 Partial Approval PETER FOLLING
Special/Order Compliance 3/9/2023 Partial Inspection MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 4/3/2023 No Access for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 4/6/2023 Corrections Issued PETER FOLLING
Excavation/Setback/Form/Re-Bar 4/11/2023 Not Ready for Inspection JUSTIN HAWLEY
Pre-Inspection 4/11/2023 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 4/12/2023 Approved PETER FOLLING
Deputy Reinf. Concrete 4/14/2023 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 4/19/2023 Partial Approval PETER FOLLING
Green Building Rough 4/19/2023 Not Ready for Inspection PETER FOLLING
MERV13>=Rough 4/19/2023 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval PETER FOLLING
Deputy Wood Construction 5/16/2023 No Access for Inspection PETER FOLLING
BUILDING-Rough-Frame 7/31/2023 Corrections Issued JON MCHUGH
Rough-Elec/Plmb/HVAC 7/31/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 8/10/2023 Partial Approval JUSTIN HAWLEY
HVAC-Rough 8/10/2023 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 8/10/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 8/17/2023 Approved PETER FOLLING
Green Building Rough 8/17/2023 Approved PETER FOLLING
Insulation 8/17/2023 Approved PETER FOLLING
Interior/Exterior Lathing 8/17/2023 Partial Approval PETER FOLLING
MERV13>=Rough 8/17/2023 Approved PETER FOLLING
Drywall Nailing 8/23/2023 Approved PETER FOLLING
Shower Pan 9/7/2023 Approved PETER FOLLING
Interior/Exterior Lathing 9/18/2023 Approved PETER FOLLING
Final 5/6/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 5/6/2024 Partial Approval GEVORK IPCHYAN
MERV13>=Final 5/6/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 5/6/2024 Approved GEVORK IPCHYAN
Final 5/9/2024 Partial Approval MORRIS JACKSON
Green Building Final 5/9/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved MORRIS JACKSON