20201 W SEPTO ST 91311

Certificate Information: 20201 W SEPTO ST 91311

Application / Permit
22014-20000-04967
Plan Check / Job No.
B22VN15076
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 SELLA BENYAMIN
Corrections Issued 11/3/2022 SELLA BENYAMIN
Quality Review Completed 11/4/2022 STEVEN KIM
Building Plans Picked Up 11/7/2022 APPLICANT
Applicant returned to address corrections 2/28/2023 SELLA BENYAMIN
Plan Check Approved 3/9/2023 SELLA BENYAMIN
Issued 6/14/2023 APPLICANT
CofO in Progress 7/1/2025 DAVID SCANTLIN
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/14/2022 MEGAN GODINEZ
Sewer availability Cleared 11/14/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/21/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 11/21/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 11/21/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 11/21/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/25/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/16/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 1/16/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 1/16/2025 Approved DAVID SCANTLIN
HVAC-Rough 1/16/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 1/16/2025 Not Ready for Inspection DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 1/21/2025 Approved DAVID SCANTLIN
Special/Order Compliance 1/21/2025 Partial Inspection JUAN ALVARADO
BUILDING-Rough-Frame 3/3/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/3/2025 Partial Approval DAVID SCANTLIN
Sewer 3/3/2025 Approved DAVID SCANTLIN
Shower Pan 3/3/2025 Approved DAVID SCANTLIN
Insulation 3/18/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 4/2/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/2/2025 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 5/14/2025 Approved KRISTEN CAUSEY
Final 6/30/2025 OK to Issue CofO DAVID SCANTLIN
Footing/Foundation/Slab 6/30/2025 Approved DAVID SCANTLIN
Green Building Final 6/30/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 6/30/2025 Approved DAVID SCANTLIN