20201 W SEPTO ST 91311
Certificate Information: 20201 W SEPTO ST 91311
- Application / Permit
- 22014-20000-04967
- Plan Check / Job No.
- B22VN15076
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | SELLA BENYAMIN |
| Corrections Issued | 11/3/2022 | SELLA BENYAMIN |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/28/2023 | SELLA BENYAMIN |
| Plan Check Approved | 3/9/2023 | SELLA BENYAMIN |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 7/1/2025 | DAVID SCANTLIN |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
| CofO Issued | 4/4/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/14/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/14/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/21/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/21/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/21/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/16/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/16/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 1/16/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 1/16/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/16/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/21/2025 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 1/21/2025 | Partial Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | DAVID SCANTLIN |
| Sewer | 3/3/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/3/2025 | Approved | DAVID SCANTLIN |
| Insulation | 3/18/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 4/2/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/2/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/14/2025 | Approved | KRISTEN CAUSEY |
| Final | 6/30/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/30/2025 | Approved | DAVID SCANTLIN |
| Green Building Final | 6/30/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 6/30/2025 | Approved | DAVID SCANTLIN |