13276 W RAVEN ST 91342
Certificate Information: 13276 W RAVEN ST 91342
- Application / Permit
- 22014-20000-04936
- Plan Check / Job No.
- B22VN14982
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN PROPOSED 32' X 41'-4" IRREGULAR SHAPED ADDITION TO EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/25/2023
- Issuing Office
- Current Status
- Issued on 2/25/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | RAPHAEL ROSAS |
| Corrections Issued | 10/18/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/2/2022 | STEVEN KIM |
| Applicant returned to address corrections | 2/9/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 2/17/2023 | RAPHAEL ROSAS |
| Issued | 2/25/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/23/2022 | DEBORA LEITE |
| Grading Pre-Inspection | Cleared | 12/12/2022 | KIRK LINKLATER |
| Address approval | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Watercourse | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/2/2023 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 2/17/2023 | RAPHAEL ROSAS |
Contact Information
| Contractor | Voskanian Razmik Thomas; Lic. No.: 909850-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/3/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/12/2023 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 4/12/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/14/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/14/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 8/14/2023 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | WILLIAM WREN |
| HVAC-Rough | 8/16/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/16/2023 | Approved | WILLIAM WREN |
| Wood Frame | 8/21/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Deputy Wood Construction | 8/24/2023 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 8/24/2023 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 8/24/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/29/2023 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 9/29/2023 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/4/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 10/10/2023 | Corrections Issued | ROBERT GOLD |
| Insulation | 11/17/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/29/2023 | Approved | ROBERT GOLD |
| Green Building Rough | 11/29/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 11/29/2023 | Approved | ROBERT GOLD |
| Service/Power Release | 3/29/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/2/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 4/2/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 4/2/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 4/2/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Final | 4/2/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/2/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 4/2/2024 | Approved | KEVIN BERBERYAN |
| Final | 4/19/2024 | Partial Approval | ROBERT GOLD |