11935 W HESBY ST 91607
Certificate Information: 11935 W HESBY ST 91607
- Application / Permit
- 22014-20000-04920
- Plan Check / Job No.
- B22VN14936
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Conversion of existing Recreation Room/Garage & Conversion of existing 8'8" x 15'10" Unpermitted Addition built prior to Jan 1, 2018 to an Accessory Dwelling Unit per 65852.23 "COMPLY WITH DEPARTMENT ORDER effective date 05/13/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector BRYAN MEYER at (818)374-9851 of GENERAL ENFORCEMENT NORTH. CEIS Case Number is 953731.
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- Issued on 7/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | PRANITA SHAH |
| Corrections Issued | 10/13/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 12/14/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 5/12/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 6/28/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 7/5/2023 | PRANITA SHAH |
| Plan Check Approved | 7/12/2023 | PRANITA SHAH |
| Issued | 7/13/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/26/2022 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 11/9/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 11/10/2022 | JOANNA MARROQUIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2023 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 11/16/2023 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 11/16/2023 | Partial Inspection | JOSE AVILA |
| HVAC-Rough | 11/16/2023 | Partial Inspection | JOSE AVILA |
| PLUMBING-Rough | 11/16/2023 | Partial Inspection | JOSE AVILA |
| Special/Order Compliance | 11/16/2023 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 2/7/2024 | Corrections Issued | BRYAN MEYER |
| ELECTRICAL-Rough | 2/7/2024 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 2/7/2024 | Corrections Issued | BRYAN MEYER |
| HVAC-Rough | 2/7/2024 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 2/7/2024 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 1/22/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| ELECTRICAL-Rough | 1/22/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 1/22/2025 | Partial Inspection | SCOTT SHUSTER |
| HVAC-Rough | 1/22/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| Order to Comply | 1/22/2025 | Not Required | SCOTT SHUSTER |
| PLUMBING-Rough | 1/22/2025 | Partial Inspection | SCOTT SHUSTER |
| Pre-Inspection | 1/22/2025 | Partial Inspection | SCOTT SHUSTER |
| Pre-Inspection | 12/2/2025 | Partial Inspection | SCOTT SHUSTER |
| Pre-Inspection | 5/5/2026 | Partial Inspection | SCOTT SHUSTER |