5818 N IRVINE AVE 91601
Certificate Information: 5818 N IRVINE AVE 91601
- Application / Permit
- 22014-20000-04898
- Plan Check / Job No.
- B22VN14844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN INTERIOR REMODEL WITH ADDITION TO (E) 1,064 SQ FT SFD AND NEW ATTACHED GARAGE
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JAD BASMA |
| Corrections Issued | 10/28/2022 | JAD BASMA |
| Quality Review Completed | 11/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/5/2023 | JAD BASMA |
| Plan Check Approved | 1/19/2023 | JAD BASMA |
| Issued | 1/19/2023 | APPLICANT |
| CofO in Progress | 9/28/2023 | JACK KARGODORIAN |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/6/2023 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/11/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/12/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/21/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/8/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 3/9/2023 | Partial Approval | JACK KARGODORIAN |
| Sewer | 4/10/2023 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 4/11/2023 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 4/18/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 4/18/2023 | Approved | JACK KARGODORIAN |
| Gas Test | 4/21/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/21/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 4/24/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/27/2023 | Partial Approval | MICHEL ABAJAN |
| Insulation | 5/8/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/8/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 5/17/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/17/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 9/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 9/13/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/13/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/13/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/19/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/19/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/19/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 9/26/2023 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 9/26/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | JACK KARGODORIAN |
| Final | 9/28/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 9/28/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/28/2023 | Approved | JACK KARGODORIAN |