5920-5922 N RIVERTON AVE 91601

Certificate Information: 5920-5922 N RIVERTON AVE 91601

Application / Permit
22014-20000-04897
Plan Check / Job No.
B22VN14842
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan A one-story addition of 776 s.f. and an attached garage conversion to and ADU of 305 s.f.
Permit Issued
Issued on 1/4/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 JAD BASMA
Corrections Issued 10/28/2022 JAD BASMA
Quality Review Completed 11/4/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/4/2023 JAD BASMA
No Progress 1/4/2023 JAD BASMA
Plan Check Approved 1/4/2023 JAD BASMA
Issued 1/4/2023 APPLICANT
CofO in Progress 2/27/2024 JOHN HAYES
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/7/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/14/2022 MEGAN GODINEZ
Sewer availability Cleared 11/14/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 12/2/2022 KURT CORRAL
Low Impact Development Cleared 12/15/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/15/2022 MEGAN GODINEZ
Hold Cleared 8/3/2023 MARIA VENDIVIL

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: NA18783       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/12/2023 Corrections Issued JOHN HAYES
Underground Mechanical 1/12/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 2/6/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/13/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/15/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Approval ROBERT GOLD
PLUMBING-Rough 7/6/2023 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/8/2023 Partial Approval RYAN SALAZAR
Insulation 7/8/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 No Access for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/7/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 8/7/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 8/7/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/9/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/9/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 8/9/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/9/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 8/15/2023 Partial Approval JOHN HAYES
Special/Order Compliance 8/15/2023 Partial Inspection JOHN HAYES
BUILDING-Rough-Frame 8/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/25/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/25/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 8/25/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 8/25/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/25/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 8/25/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/29/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 8/29/2023 Approved JOHN HAYES
Green Building Rough 8/29/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 8/29/2023 Approved ROBERT GOLD
Special/Order Compliance 8/29/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 9/5/2023 Approved ROBERT GOLD
Green Building Rough 9/5/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 9/5/2023 Partial Approval ROBERT GOLD
Insulation 9/18/2023 Approved JOHN HAYES
Insulation 9/23/2023 Approved RYAN SALAZAR
Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/27/2023 Approved JENNIFER RABUCHIN
Green Building Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 11/27/2023 Approved JENNIFER RABUCHIN
Final 1/3/2024 Corrections Issued JOHN HAYES
Green Building Final 1/3/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Not Ready JOHN HAYES
Final 2/15/2024 Partial Inspection CRAIG DAVIS
Green Building Final 2/15/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved CRAIG DAVIS
Final 2/21/2024 OK to Issue CofO JOHN HAYES
Green Building Final 2/21/2024 Approved JOHN HAYES