6945 N ETHEL AVE 91605
Certificate Information: 6945 N ETHEL AVE 91605
- Application / Permit
- 22014-20000-04892
- Plan Check / Job No.
- B22VN14837
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) DETACHED GARAGE TO A SFD WITH AN ADDITION PER SB9 (1-STORY)
- Permit Issued
- Issued on 3/4/2023
- Issuing Office
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | CARLOS MONTES |
| Corrections Issued | 10/29/2022 | CARLOS MONTES |
| Quality Review Completed | 10/31/2022 | GARO TELMI |
| Plan Check Approved | 3/3/2023 | CARLOS MONTES |
| Issued | 3/4/2023 | APPLICANT |
| CofO in Progress | 11/12/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/2/2025 | RUBEN SALAS |
| CofO Issued | 1/2/2025 | RUBEN SALAS |
| Permit Finaled | 1/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/7/2022 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 2/3/2023 | STEVEN WECHSLER |
| ZA Case | Cleared | 2/3/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Underground Mechanical | 4/11/2023 | Approved | JOHN COLEMAN |
| Underground Mechanical | 4/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/18/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 5/8/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/31/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/31/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 5/31/2024 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 6/5/2024 | Approved | JOSE AVILA |
| Wood Frame | 6/12/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/17/2024 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 6/27/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/9/2024 | Approved | LEONARD ROSS II |
| Shower Pan | 7/9/2024 | No Access for Inspection | LEONARD ROSS II |
| Shower Pan | 7/15/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 9/30/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 10/22/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 10/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 10/31/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/8/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 11/8/2024 | Approved | OGANES TARAKHCHYAN |