6421 N GENTRY AVE 91606

Certificate Information: 6421 N GENTRY AVE 91606

Application / Permit
22014-20000-04884
Plan Check / Job No.
B22VN14808
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
43'-0" X 33'-0" IRREGULAR SHAPED ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEER
Permit Issued
Issued on 3/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 ARTIN ZARUKIAN
Corrections Issued 10/5/2022 ARTIN ZARUKIAN
Building Plans Picked Up 10/24/2022 APPLICANT
Applicant returned to address corrections 3/17/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 3/21/2023 ALFRED RAMIREZ
Issued 3/24/2023 APPLICANT
CofO in Progress 12/6/2023 JOHN HAYES
Permit Finaled 4/11/2024 RUBEN SALAS
CofO Issued 4/11/2024 RUBEN SALAS
Permit Finaled 4/11/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/1/2022 CARLOS AGUILERA
Sewer availability Cleared 11/1/2022 CARLOS AGUILERA
Low Impact Development Cleared 3/10/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 3/14/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/5/2023 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 4/6/2023 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/11/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 4/11/2023 Not Ready for Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 4/20/2023 Approved JOHN HAYES
Footing/Foundation/Slab 4/20/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 6/9/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 6/9/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 6/9/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/9/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/13/2023 Approved JOHN HAYES
Green Building Rough 7/13/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 7/13/2023 Approved JOHN HAYES
Insulation 7/19/2023 Approved JOHN HAYES
Interior/Exterior Lathing 7/19/2023 Approved JOHN HAYES
Shower Pan 7/19/2023 Approved JOHN HAYES
Drywall Nailing 7/25/2023 Approved JOHN HAYES
Interior/Exterior Lathing 7/25/2023 Approved JOHN HAYES
Gas Test 8/31/2023 Partial Approval JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready JOHN HAYES
Underground Mechanical 8/31/2023 Partial Approval JOHN HAYES
Underground Mechanical 9/18/2023 Approved JOHN HAYES
ELECTRICAL-Final 10/17/2023 Corrections Issued JENNIFER RABUCHIN
Final 10/17/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/17/2023 Approved JENNIFER RABUCHIN
HVAC-Final 10/17/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/17/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 10/17/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/17/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/2/2023 Approved JENNIFER RABUCHIN
Final 11/2/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/2/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/2/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved JENNIFER RABUCHIN
Final 12/5/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 12/6/2023 Approved JOHN HAYES