435 1/2 E 60TH ST 90003
Certificate Information: 435 1/2 E 60TH ST 90003
- Application / Permit
- 22014-20000-04878
- Plan Check / Job No.
- B22VN14776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' x 16' GARAGE AND (N) 19'2"x 14'4" ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Current Status
- Issued on 12/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | JEFFREY TANGONAN |
| Corrections Issued | 10/6/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 10/6/2022 | APPLICANT |
| Plan Check Approved | 12/5/2022 | MADISON ODELL |
| Issued | 12/5/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/17/2022 | STEVE MELGAR |
| Address approval | Cleared | 10/19/2022 | STEVE MELGAR |
| Construction within easement | Cleared | 12/1/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/17/2025 | Partial Approval | MICHAEL LEWIS |
| Sewer | 9/17/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/17/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Partial Approval | MICHAEL LEWIS |
| Pre-Inspection | 11/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/26/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 11/26/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 11/26/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 11/26/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/12/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 12/12/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/12/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/12/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/23/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 1/2/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/2/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 1/27/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 1/27/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/10/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 2/27/2026 | Approved | LUIS CASTRO |
| Final | 4/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/15/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/15/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 5/15/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/15/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/15/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Final | 5/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/21/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 5/21/2026 | Approved | ALEJANDRO DE ARTOLA |