3324 N PORTOLA AVE 90032

Certificate Information: 3324 N PORTOLA AVE 90032

Application / Permit
22014-20000-04866
Plan Check / Job No.
B22VN14752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) SFD TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & EXPAND (E) DINING ROOM & ADD (N) BEDROOM & LIVING ROOM (IRR 37'-3" X 17'-4"); INTERIOR REMODEL; ADD (N) UNCOVERED DECK (IRR 21'-6" X 8') [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
Permit Issued
Issued on 2/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 NILOOFAR MEHRAIN
Corrections Issued 10/11/2022 NILOOFAR MEHRAIN
Quality Review Completed 10/19/2022 STEVEN KIM
Building Plans Picked Up 10/24/2022 APPLICANT
Plan Check Approved 1/27/2023 NILOOFAR MEHRAIN
Issued 2/17/2023 APPLICANT
CofO in Progress 10/28/2024 LILIANA PORTILLO
Permit Finaled 11/13/2024 DEROLD HAUFF
CofO Issued 11/13/2024 DEROLD HAUFF
Permit Finaled 11/13/2024 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 10/10/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/19/2022 KIRK LINKLATER
Address approval Cleared 1/3/2023 AMAAN MALIK
Sewer availability Cleared 1/3/2023 AMAAN MALIK
Hydrant and Access approval Cleared 1/4/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 1/6/2023 AMAAN MALIK
"D" conditions Cleared 1/13/2023 RUBEN VASQUEZ
"Q" conditions Cleared 1/13/2023 RUBEN VASQUEZ
ZI Cleared 1/13/2023 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 1/27/2023 AMAAN MALIK

Contact Information

Contractor Aiden'S Structural Concepts; Lic. No.: 922303-B 13230 BROMONT AVE #111      SYLMAR, CA 91342
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2024 Approved LILIANA PORTILLO
Insulation 4/12/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 5/23/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/30/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 5/30/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 5/30/2024 Corrections Issued LILIANA PORTILLO
Sewer 5/30/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 5/30/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/5/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/5/2024 Approved LILIANA PORTILLO
Green Building Rough 6/5/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 6/5/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/5/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 6/5/2024 Approved LILIANA PORTILLO
Insulation 6/20/2024 Approved LILIANA PORTILLO
Shower Pan 6/20/2024 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 6/25/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/25/2024 Partial Approval LILIANA PORTILLO
Shower Pan 6/25/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/22/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/27/2024 Approved BRENDAN MORELLI
Green Building Rough 9/27/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Not Ready BRENDAN MORELLI
ELECTRICAL-Final 9/30/2024 Not Ready for Inspection LILIANA PORTILLO
Final 9/30/2024 Corrections Issued LILIANA PORTILLO
HVAC-Final 9/30/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 9/30/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 10/21/2024 Approved LILIANA PORTILLO
Final 10/21/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 10/21/2024 Approved LILIANA PORTILLO
HVAC-Final 10/21/2024 Approved LILIANA PORTILLO
PLUMBING-Final 10/21/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 10/21/2024 Approved LILIANA PORTILLO
Final 10/23/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 10/23/2024 Approved LILIANA PORTILLO
Final 10/25/2024 OK to Issue CofO LILIANA PORTILLO