13189 N FELLOWS AVE 91342
Certificate Information: 13189 N FELLOWS AVE 91342
- Application / Permit
- 22014-20000-04863
- Plan Check / Job No.
- B22VN14744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 20'X24' GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 25'6"X13' ADDITION. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 10/5/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/24/2022 | APPLICANT |
| Applicant returned to address corrections | 5/12/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/17/2023 | ISIS ARGUETA |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2022 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | RYAN KIM |
| Sewer availability | Cleared | 4/11/2023 | RYAN KIM |
| Community Plan Implem. Overlay | Cleared | 4/21/2023 | CECILIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/31/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/8/2023 | Approved | WILLIAM WREN |
| Deputy Drilled-In Anchors | 8/14/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/5/2023 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 9/15/2023 | Conditional Approval | ROBERT GOLD |
| HVAC-Rough | 9/15/2023 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/15/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/19/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/4/2023 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 10/4/2023 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/11/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 10/11/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/25/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/17/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/17/2023 | Approved | KEVIN BERBERYAN |
| Final | 2/14/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 2/14/2024 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 2/14/2024 | Corrections Issued | JOHN COLEMAN |
| Gas Test | 2/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 2/23/2024 | Approved | MICHEL ABAJAN |
| Final | 2/27/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 2/27/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 2/27/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/22/2024 | OK to Issue CofO | KEVIN BERBERYAN |