5335 N DON PIO DR 91364

Certificate Information: 5335 N DON PIO DR 91364

Application / Permit
22014-20000-04859
Plan Check / Job No.
B22VN14734
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 13'-0" x 20'-6" ADDITION TO AND CONVERT 18'-0" x 20'-0" (E) DET. GARAGE TO A NEW (556.5 S.F) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 JESSE ARELLANO
Corrections Issued 10/6/2022 JESSE ARELLANO
Building Plans Picked Up 10/11/2022 APPLICANT
Plan Check Approved 11/10/2022 SARKIS HARABEDIAN
Issued 11/10/2022 APPLICANT
CofO in Progress 2/23/2024 MORRIS JACKSON
Permit Finaled 3/14/2024 JOHN JANSON
CofO Issued 3/14/2024 JOHN JANSON
Permit Finaled 3/14/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/6/2022 JESSE ARELLANO
Address approval Cleared 11/4/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/4/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/4/2022 COLIN LOREDO
Sewer availability Cleared 11/4/2022 COLIN LOREDO
Construction near power lines Cleared 11/10/2022 JOHN BACON

Contact Information

Contractor Fire Guard Corporation; Lic. No.: 847796-B 6603 INDEPENDENCE AVENUE A      CANOGA PARK, CA 91303

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2023 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 7/21/2023 No Access for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 7/24/2023 Approved PETER FOLLING
Footing/Foundation/Slab 7/24/2023 Approved PETER FOLLING
ELECTRICAL-Rough 8/14/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Corrections Issued PETER FOLLING
HVAC-Rough 8/14/2023 Approved PETER FOLLING
PLUMBING-Rough 8/14/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 8/17/2023 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 8/31/2023 Approved PETER FOLLING
Green Building Rough 8/31/2023 Approved PETER FOLLING
Insulation 8/31/2023 Approved PETER FOLLING
Interior/Exterior Lathing 8/31/2023 Partial Approval PETER FOLLING
Drywall Nailing 9/6/2023 Approved PETER FOLLING
Shower Pan 9/6/2023 Approved PETER FOLLING
Interior/Exterior Lathing 9/11/2023 Approved PETER FOLLING
Service/Power Release 11/6/2023 Not Ready for Inspection PETER FOLLING
Service/Power Release 12/7/2023 Approved JOHN KIDWELL
Final 12/12/2023 Corrections Issued JOHN KIDWELL
Green Building Final 12/12/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 12/12/2023 Approved JOHN KIDWELL
Final 1/10/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 1/10/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready JOHN KIDWELL
Final 1/18/2024 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Approved JOHN KIDWELL
ELECTRICAL-Final 2/13/2024 Approved MORRIS JACKSON
Final 2/13/2024 Partial Approval MORRIS JACKSON
HVAC-Final 2/13/2024 Approved MORRIS JACKSON
PLUMBING-Final 2/13/2024 Approved MORRIS JACKSON
Final 2/14/2024 Partial Approval MORRIS JACKSON
Final 2/21/2024 Corrections Issued MORRIS JACKSON
Final 2/22/2024 OK to Issue CofO MORRIS JACKSON