8918 W CADILLAC AVE 90034
Certificate Information: 8918 W CADILLAC AVE 90034
- Application / Permit
- 22014-20000-04858
- Plan Check / Job No.
- B22VN14733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX 20' x 18' GARAGE AND ADD 12' x 10'-8" FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | JEFFREY TANGONAN |
| Corrections Issued | 10/4/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 10/11/2022 | APPLICANT |
| Plan Check Approved | 12/13/2022 | SARKIS HARABEDIAN |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 7/3/2023 | ARAM AVEDISIAN |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/14/2022 | TREVOR QUAN |
| Construction within easement | Cleared | 12/13/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/15/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 2/16/2023 | Conditional Approval | DAVID FEILER |
| PLUMBING-Rough | 2/21/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 3/3/2023 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 3/3/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/3/2023 | Not Ready for Inspection | JEREMY TODD |
| ELECTRICAL-Rough | 4/3/2023 | Approved | JEREMY TODD |
| Green Building Rough | 4/3/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/3/2023 | Approved | JEREMY TODD |
| Wood Frame | 4/3/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 4/5/2023 | Approved | JEREMY TODD |
| Insulation | 4/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/11/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/14/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | JEREMY TODD |
| Final | 5/11/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 5/11/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 5/11/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/18/2023 | Approved | JEREMY TODD |
| HVAC-Final | 5/18/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/18/2023 | Approved | JEREMY TODD |
| Final | 6/22/2023 | Corrections Issued | JEREMY TODD |
| Final | 7/3/2023 | OK to Issue CofO | ARAM AVEDISIAN |