5756 N FALLBROOK AVE 91367

Certificate Information: 5756 N FALLBROOK AVE 91367

Application / Permit
22014-20000-04843
Plan Check / Job No.
B22VN14677
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING (20'-0"x24'-0"), 480 SQFT DETACHED GARAGE INTO ADU W/ 1ST AND 2ND FLOOR ADDITION (20'-6"x19'-0"), 711 SQFT PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 6/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 PETER MOSESIAN
Corrections Issued 10/26/2022 PETER MOSESIAN
Quality Review Completed 10/28/2022 OMID HEDAYAT
Building Plans Picked Up 10/31/2022 APPLICANT
Plan Check Approved 11/16/2022 PETER MOSESIAN
Issued 6/6/2023 APPLICANT
CofO in Progress 4/25/2025 TROY SANDERS
Permit Finaled 6/2/2025 JOHN JANSON
CofO Issued 6/2/2025 JOHN JANSON
Permit Finaled 6/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/2/2022 LUCIA MERCADO
Roof/Waste drainage to street Cleared 11/2/2022 LUCIA MERCADO
Eng Process Fee Ord 176,300 Cleared 11/3/2022 LUCIA MERCADO
Sewer availability Cleared 11/3/2022 LUCIA MERCADO
ZA Case Cleared 11/6/2022 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2023 Not Ready for Inspection HORACE FULTZ
PLUMBING-Rough 6/9/2023 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 6/16/2023 Approved JUSTIN HAWLEY
Drywall Nailing 7/3/2023 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Approval MORRIS JACKSON
Green Building Rough 7/3/2023 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Conditional Approval TROY SANDERS
Special/Order Compliance 7/21/2023 Corrections Issued TROY SANDERS
PLUMBING-Rough 8/9/2023 Approved TROY SANDERS
ELECTRICAL-Rough 9/14/2023 Approved MORRIS JACKSON
HVAC-Final 9/14/2023 Approved MORRIS JACKSON
HVAC-Rough 9/14/2023 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Final 9/14/2023 Approved MORRIS JACKSON
HVAC-Rough 9/20/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 9/20/2023 Approved MORRIS JACKSON
ELECTRICAL-Final 10/4/2023 Not Ready for Inspection TROY SANDERS
Service/Power Release 10/4/2023 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 11/30/2023 Approved TROY SANDERS
Green Building Rough 11/30/2023 Approved TROY SANDERS
ELECTRICAL-Final 12/8/2023 Corrections Issued MORRIS JACKSON
Insulation 12/19/2024 Approved TROY SANDERS
Drywall Nailing 12/31/2024 Approved TROY SANDERS
Shower Pan 1/14/2025 Approved TROY SANDERS
Interior/Exterior Lathing 1/21/2025 Partial Approval TROY SANDERS
ELECTRICAL-Final 2/5/2025 Approved TROY SANDERS
Service/Power Release 2/5/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready TROY SANDERS
Final 3/21/2025 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved JON MCHUGH
Smoke Detectors 3/21/2025 Approved JON MCHUGH
Final 4/24/2025 OK to Issue CofO TROY SANDERS
Green Building Final 4/24/2025 Approved TROY SANDERS
Special/Order Compliance 5/1/2025 Approved TROY SANDERS