18424 W HALSTED ST 1-41 91325
Certificate Information: 18424 W HALSTED ST 1-41 91325
- Application / Permit
- 22014-20000-04837
- Plan Check / Job No.
- B22VN14657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EX. PARKING AREA/ GARAGE INTO (2) ACCESSORY DWELLING UNITS ( UNITS #40 AND #41 ) PER CA. GOV. STATE CODE 65852.2(e)(1)(C) FOR EX. 39-UNIT APARTMENT. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/24/2023
- Issuing Office
- Current Status
- CofO Issued on 5/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | ROSENDO MEDINA |
| Corrections Issued | 10/7/2022 | ROSENDO MEDINA |
| Plan Check Approved | 2/22/2023 | ROSENDO MEDINA |
| Issued | 2/24/2023 | APPLICANT |
| CofO in Progress | 5/21/2025 | DEANDRE HOFFMAN |
| Permit Finaled | 5/21/2025 | JEFFREY DURAN |
| CofO Issued | 5/21/2025 | JEFFREY DURAN |
| Permit Finaled | 5/21/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 11/17/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | FERNANDO GIL |
| Fire Marshal Fire Life Safety | Cleared | 1/31/2023 | WILLIAM JOHNS |
| Tenant Habitability Plan | Cleared | 2/7/2023 | MICHAEL SOTO |
Contact Information
| Contractor | Working Hands Builders Inc; Lic. No.: 1059742-B | , |
| Contractor | Z And J Manufacturing Group Inc; Lic. No.: 1059742-B | , |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 6/26/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 6/26/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 6/26/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 7/14/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 9/12/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 9/12/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 9/12/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 11/14/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 11/14/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 11/14/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 1/12/2024 | Approved | KENNETH ROBERTS |
| Wood Frame | 1/12/2024 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 2/1/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 3/14/2024 | Partial Inspection | KENNETH ROBERTS |
| Special/Order Compliance | 3/20/2024 | Corrections Issued | KENNETH ROBERTS |
| Insulation | 3/26/2024 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 3/29/2024 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 4/2/2024 | Approved | DEANDRE HOFFMAN |
| Final | 5/3/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 5/3/2024 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 5/3/2024 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 5/3/2024 | Approved | DEANDRE HOFFMAN |
| Final | 5/21/2025 | OK to Issue CofO | DEANDRE HOFFMAN |