19608-19610 W MAYALL ST 91324

Certificate Information: 19608-19610 W MAYALL ST 91324

Application / Permit
22014-20000-04833
Plan Check / Job No.
B22VN14647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-3" x 5'-5" ADDITION TO & CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). WORK DONE PER ENGINEER
Permit Issued
Issued on 10/7/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/30/2022 ARTIN ZARUKIAN
Corrections Issued 10/1/2022 ARTIN ZARUKIAN
Building Plans Picked Up 10/4/2022 APPLICANT
Issued 10/7/2022 APPLICANT
CofO in Progress 12/18/2024 DAVID SCANTLIN
CofO Issued 12/18/2024 JOHN JANSON
Permit Finaled 12/18/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/5/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/6/2022 COLIN LOREDO
Sewer availability Cleared 10/7/2022 COLIN LOREDO

Contact Information

Contractor Home Top Construction & Design Inc; Lic. No.: 939788-B 6931 VAN NUYS BLVD #307      VAN NUYS, CA 91405
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/17/2022 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 10/19/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 10/31/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/12/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Approved DAVID SCANTLIN
Wood Frame 12/12/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 12/29/2022 Approved DAVID SCANTLIN
HVAC-Rough 12/29/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 12/29/2022 Approved DAVID SCANTLIN
Wood Frame 12/29/2022 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 1/10/2023 Approved DAVID SCANTLIN
Green Building Rough 1/10/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/10/2023 Partial Approval DAVID SCANTLIN
Shower Pan 1/10/2023 Approved DAVID SCANTLIN
Drywall Nailing 1/24/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 1/24/2023 Approved MORRIS JACKSON
Final 3/29/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 3/29/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 3/29/2023 Approved DAVID SCANTLIN
Final 4/12/2023 Partial Approval DAVID SCANTLIN
Green Building Final 4/12/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved DAVID SCANTLIN
Final 12/18/2024 OK to Issue CofO DAVID SCANTLIN