10643 W SOMMA WAY 90077

Certificate Information: 10643 W SOMMA WAY 90077

Application / Permit
22014-20000-04830
Plan Check / Job No.
B22VN14640
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2'-6" x 12'-10" ADDITION TO (E) KITCHEN (32 SF) @ 1ST FLOOR, ADD NEW FRONT PORCH (132 SF), IRR. SHAPED ADDITION (230 SF) @ 2ND FLOOR TO ADD NEW BEDROOM/BATHROOM, , AND REMODEL (E) SINGLE FAMILY DWELLING W/ ATT. GARAGE
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
Issued on 5/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 SEAN SHAHMIRI
Corrections Issued 10/11/2022 SEAN SHAHMIRI
Quality Review Completed 10/11/2022 OMID HEDAYAT
Building Plans Picked Up 10/11/2022 APPLICANT
Applicant returned to address corrections 2/23/2023 SEAN SHAHMIRI
Plan Check Approved 5/25/2023 SEAN SHAHMIRI
Issued 5/25/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2022 JENSON LEE
Roof/Waste drainage to street Cleared 10/19/2022 JENSON LEE
Sewer availability Cleared 10/19/2022 JENSON LEE
Hydrant and Access approval Cleared 11/12/2022 GILBERT URREA

Contact Information

Architect Larkin,, Dean A; Lic. No.: C28277 8912 HOLLYWOOD HILLS RD      LOS ANGELES, CA 90046
Contractor Herman Construction Company; Lic. No.: 656342-B 107 N REINO RD #408      NEWBURY PARK, CA 91320
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2023 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 11/17/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/1/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/4/2024 Approved CHRISTOPHER WILSON
Deputy Wood Construction 7/11/2024 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 11/20/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 11/22/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 1/15/2025 Partial Approval REGINA MENDEZ
ELECTRICAL-Rough 2/4/2025 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 2/4/2025 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 2/4/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 2/11/2025 Corrections Issued BOBBY KEY
Insulation 2/11/2025 Partial Approval BOBBY KEY
Shower Pan 2/11/2025 Approved BOBBY KEY
ELECTRICAL-Rough 2/14/2025 Approved SEAN HAUPT
HVAC-Rough 2/14/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/18/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 2/18/2025 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 2/21/2025 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/21/2025 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/11/2025 Partial Approval CHRISTOPHER WILSON
Green Building Rough 3/11/2025 Partial Approval CHRISTOPHER WILSON
Insulation 3/11/2025 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/11/2025 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/19/2025 Approved CHRISTOPHER WILSON
Green Building Rough 3/19/2025 Approved CHRISTOPHER WILSON
Insulation 3/19/2025 Approved CHRISTOPHER WILSON
Drywall Nailing 3/28/2025 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 7/2/2025 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 8/25/2025 Approved CHRISTOPHER WILSON
Underground Mechanical 11/18/2025 Approved CARLOS MATAMOROS
Gas Test 12/8/2025 Partial Approval CHRISTOPHER WILSON
Sewer 12/8/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 12/10/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 12/16/2025 Corrections Issued CHRISTOPHER WILSON
Sewer 12/16/2025 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 1/29/2026 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 1/29/2026 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 2/6/2026 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 2/11/2026 Approved CARLOS MATAMOROS
Pre-Inspection 4/30/2026 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Final 5/6/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved RYAN SALAZAR
HVAC-Final 5/13/2026 Approved RYAN SALAZAR