6373 W 78TH ST 90045

Certificate Information: 6373 W 78TH ST 90045

Application / Permit
22014-20000-04826
Plan Check / Job No.
B22VN14626
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL INT. & EXT. WALLS EXCEPT FOR SOME OF THE WALLS AROUND THE (E) GARAGE AND ERECT A 2-STORY 65'-8" x 48'-5" SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE; NFPA-13D THRU-OUT
Permit Issued
Issued on 1/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 SEAN SHAHMIRI
Corrections Issued 10/11/2022 SEAN SHAHMIRI
Quality Review Completed 10/11/2022 OMID HEDAYAT
Building Plans Picked Up 10/17/2022 APPLICANT
Plan Check Approved 12/19/2022 SEAN SHAHMIRI
Issued 1/25/2023 APPLICANT
CofO in Progress 11/14/2023 HERBERT GIRON
Permit Finaled 11/18/2023 DANIEL ORRANTE
CofO Issued 11/18/2023 DANIEL ORRANTE
Permit Finaled 11/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/21/2022 LAVEON RIDER
Permit Cleared 10/22/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 10/26/2022 DINAH GARIN
Sewer availability Cleared 10/26/2022 DINAH GARIN
Trees in Parkway Cleared 11/18/2022 ADALBERTO VERA
Low Impact Development Cleared 12/2/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/6/2022 DINAH GARIN

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403
Geologist Siskowic,, John Gary; Lic. No.: GEO8255 515 S CATALINA AVE APT A      REDONDO BEACH, CA 90277

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/27/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/2/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 3/8/2023 Partial Approval HERBERT GIRON
METHANE-Barrier 3/8/2023 Approved HERBERT GIRON
METHANE-Subgrade 3/8/2023 Approved HERBERT GIRON
Deputy Drilled-In Anchors 3/20/2023 Approved HERBERT GIRON
Deputy Reinf. Concrete 3/20/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 3/20/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 4/18/2023 Conditional Approval HERBERT GIRON
Deputy Wood Construction 6/2/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 6/20/2023 Approved RICHARD STEINBACH
PLUMBING-Rough 6/20/2023 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 6/21/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 6/21/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/28/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 6/28/2023 Approved HERBERT GIRON
Green Building Rough 6/28/2023 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 6/28/2023 Partial Approval HERBERT GIRON
Sewer 6/28/2023 Approved HERBERT GIRON
Shower Pan 6/28/2023 Approved HERBERT GIRON
Underground Mechanical 6/28/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 6/28/2023 Approved HERBERT GIRON
Insulation 7/3/2023 Approved RICHARD STEINBACH
Drywall Nailing 7/10/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 7/10/2023 Approved HERBERT GIRON
Deputy Drilled-In Anchors 10/2/2023 Conditional Approval HERBERT GIRON
Deputy Reinf. Concrete 10/2/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Final 11/6/2023 Approved HERBERT GIRON
HVAC-Final 11/6/2023 Approved HERBERT GIRON
PLUMBING-Final 11/7/2023 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 11/9/2023 Approved HERBERT GIRON
PLUMBING-Final 11/9/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved HERBERT GIRON
Service/Power Release 11/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/13/2023 Approved HERBERT GIRON
Final 11/13/2023 OK to Issue CofO HERBERT GIRON
Green Building Final 11/13/2023 Approved HERBERT GIRON
Green Building Rough 11/13/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/13/2023 Approved HERBERT GIRON