15077 W ORO GRANDE ST 91342

Certificate Information: 15077 W ORO GRANDE ST 91342

Application / Permit
22014-20000-04817
Plan Check / Job No.
B22VN14607
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION (271.5 SF) TO (E) 1-STORY SFD.
Permit Issued
Issued on 1/12/2023
Issuing Office
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2022 APPLICANT
Assigned to Plan Check Engineer 10/19/2022 VIVIAN LAO
Corrections Issued 10/20/2022 VIVIAN LAO
Plan Check Approved 12/21/2022 DANIEL YIP
Issued 1/12/2023 APPLICANT
CofO in Progress 11/12/2025 JENNIFER RABUCHIN
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/24/2022 MEGAN GODINEZ
Sewer availability Cleared 10/24/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/25/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 10/25/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 10/25/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 10/25/2022 MEGAN GODINEZ
Grading Pre-Inspection Cleared 11/4/2022 VASIL MIHALEV
Tenant Habitability Plan Cleared 11/9/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2023 Partial Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 2/14/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 2/23/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 2/23/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/23/2023 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/4/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/15/2023 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/23/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 7/21/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 7/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/21/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/31/2023 Corrections Issued ROBERT GOLD
HVAC-Rough 7/31/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 7/31/2023 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 8/9/2023 Corrections Issued DAVID MATSON
HVAC-Rough 8/9/2023 Approved DAVID MATSON
PLUMBING-Rough 8/9/2023 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 8/14/2023 Partial Approval THOMAS FINNILA
HVAC-Rough 8/14/2023 Approved THOMAS FINNILA
PLUMBING-Rough 8/14/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 8/25/2023 Approved JENNIFER RABUCHIN
Green Building Final 8/25/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 8/25/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/25/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 9/11/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 9/11/2023 Not Ready for Inspection ROBERT GOLD
Insulation 9/11/2023 Corrections Issued ROBERT GOLD
Insulation 9/15/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/26/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 9/26/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 9/26/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 9/28/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/19/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/3/2024 Corrections Issued JENNIFER RABUCHIN
Sewer 4/3/2024 Corrections Issued JENNIFER RABUCHIN
Sewer 4/25/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/10/2025 Approved JENNIFER RABUCHIN
Final 11/10/2025 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 11/10/2025 Approved JENNIFER RABUCHIN
HVAC-Final 11/10/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/10/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved JENNIFER RABUCHIN
Sewer 11/10/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 11/10/2025 Approved JENNIFER RABUCHIN