10841 W PEACH GROVE ST 91601
Certificate Information: 10841 W PEACH GROVE ST 91601
- Application / Permit
- 22014-20000-04816
- Plan Check / Job No.
- B22VN14604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan New ADU addition to (E) garage. PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Current Status
- CofO Issued on 5/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | DANIEL SANJUAN |
| Corrections Issued | 10/5/2022 | DANIEL SANJUAN |
| Plan Check Approved | 11/8/2022 | DANIEL SANJUAN |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 4/11/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
| CofO Issued | 5/8/2024 | RUBEN SALAS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/31/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 11/3/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/4/2022 | JOHN LIN |
Contact Information
| Architect | Karabachian,, Sevak A; Lic. No.: NA38632 | , |
| Contractor | Golden Point Construction; Lic. No.: 965193-B | , |
| Engineer | Arakelyan,, Aram; Lic. No.: NA82796 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/17/2023 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/19/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/31/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/2/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/30/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 6/9/2023 | Approved | JACK KARGODORIAN |
| Insulation | 6/15/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/15/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 6/26/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 7/11/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/18/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 3/20/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 3/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 3/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 3/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 3/22/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/22/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 3/22/2024 | Approved | KIRK SANDERS |
| Final | 3/28/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 4/10/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Approved | CHRISTOPHER ROJAS |