10841 W PEACH GROVE ST 91601

Certificate Information: 10841 W PEACH GROVE ST 91601

Application / Permit
22014-20000-04816
Plan Check / Job No.
B22VN14604
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan New ADU addition to (E) garage. PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/12/2022
Issuing Office
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2022 APPLICANT
Assigned to Plan Check Engineer 10/4/2022 DANIEL SANJUAN
Corrections Issued 10/5/2022 DANIEL SANJUAN
Plan Check Approved 11/8/2022 DANIEL SANJUAN
Issued 12/12/2022 APPLICANT
CofO in Progress 4/11/2024 CHRISTOPHER ROJAS
Permit Finaled 5/8/2024 RUBEN SALAS
CofO Issued 5/8/2024 RUBEN SALAS
Permit Finaled 5/8/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/18/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/18/2022 COLIN LOREDO
Sewer availability Cleared 10/31/2022 COLIN LOREDO
Low Impact Development Cleared 11/3/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 11/4/2022 JOHN LIN

Contact Information

Architect Karabachian,, Sevak A; Lic. No.: NA38632       ,
Contractor Golden Point Construction; Lic. No.: 965193-B       ,
Engineer Arakelyan,, Aram; Lic. No.: NA82796       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/17/2023 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 1/19/2023 Approved JACK KARGODORIAN
Footing/Foundation/Slab 1/19/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 1/31/2023 Partial Approval JACK KARGODORIAN
Insulation 2/2/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 3/30/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/16/2023 Approved JACK KARGODORIAN
HVAC-Rough 5/16/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 5/16/2023 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 5/16/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/9/2023 Approved JACK KARGODORIAN
Green Building Rough 6/9/2023 Approved JACK KARGODORIAN
Insulation 6/15/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/15/2023 Partial Approval JACK KARGODORIAN
Drywall Nailing 6/26/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/11/2023 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 7/11/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/18/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 3/20/2024 Not Ready for Inspection KIRK SANDERS
Final 3/20/2024 Corrections Issued KIRK SANDERS
Green Building Final 3/20/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Final 3/20/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 3/20/2024 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 3/20/2024 Not Ready for Inspection KIRK SANDERS
Final 3/22/2024 Corrections Issued KIRK SANDERS
Green Building Final 3/22/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 3/22/2024 Approved KIRK SANDERS
Final 3/28/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Final 4/10/2024 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved CHRISTOPHER ROJAS