17388 W SUNSET RIDGE CIR 91344

Certificate Information: 17388 W SUNSET RIDGE CIR 91344

Application / Permit
22014-20000-04791
Plan Check / Job No.
B22VN14499
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 25'-10" X 18'-2"ADDITION TO THE (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/3/2023
Issuing Office
Current Status
Issued on 5/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2022 APPLICANT
Assigned to Plan Check Engineer 10/3/2022 OMAR GARNICA
Corrections Issued 10/4/2022 OMAR GARNICA
Applicant returned to address corrections 4/8/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/14/2023 LUISANGEL VALENZUELA
Plan Check Approved 5/2/2023 LUISANGEL VALENZUELA
Issued 5/3/2023 APPLICANT

Permit Application Clearance Information

Tract Map conditions Cleared 2/24/2023 DANG NGUYEN
ZA Case Cleared 2/24/2023 DANG NGUYEN
Low Impact Development Cleared 3/14/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 3/15/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/16/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/16/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 3/16/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: NA58024       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/19/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 5/19/2023 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 5/19/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 5/26/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 7/17/2023 Corrections Issued STEVEN BACK
HVAC-Rough 7/17/2023 Approved STEVEN BACK
PLUMBING-Rough 7/17/2023 Approved STEVEN BACK
ELECTRICAL-Rough 7/26/2023 Approved STEVEN BACK
Interior/Exterior Lathing 7/26/2023 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/9/2023 No Access for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/10/2023 Approved HORACE FULTZ
Insulation 8/21/2023 Approved STEVEN BACK
Drywall Nailing 8/29/2023 Approved DAVID SCANTLIN
Shower Pan 9/8/2023 Approved HENRY KIM
Interior/Exterior Lathing 9/19/2023 Partial Approval HENRY KIM
Special/Order Compliance 9/19/2023 Approved HENRY KIM
Special/Order Compliance 9/27/2023 Approved STEVEN BACK
Pre-Inspection 2/1/2024 Approved STEVEN BACK
ELECTRICAL-Final 10/7/2024 Approved STEVEN BACK
PLUMBING-Final 10/7/2024 Approved STEVEN BACK