9618 N ODESSA AVE 91343

Certificate Information: 9618 N ODESSA AVE 91343

Application / Permit
22014-20000-04781
Plan Check / Job No.
B22VN14464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITON OF 6'-6" x 6'-6" TO (E) S.F.D. TO EXPAND BATHROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 10/7/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/26/2022 HAYATO TSUCHIYA
Corrections Issued 9/26/2022 HAYATO TSUCHIYA
Issued 10/7/2022 APPLICANT
CofO in Progress 2/24/2023 RAUL OLAGI
CofO Issued 3/6/2023 MICHAEL SMITH
Permit Finaled 3/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 9/27/2022 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 9/28/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/28/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 10/6/2022 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/14/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/14/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/24/2022 Approved RAUL OLAGI
PLUMBING-Rough 10/24/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 11/18/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 11/18/2022 Approved RAUL OLAGI
HVAC-Rough 11/18/2022 Approved RAUL OLAGI
PLUMBING-Rough 11/18/2022 Approved RAUL OLAGI
Green Building Rough 11/22/2022 Approved RAUL OLAGI
Insulation 11/22/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/22/2022 Approved RAUL OLAGI
Drywall Nailing 12/1/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 12/1/2022 Approved RAUL OLAGI
ELECTRICAL-Final 1/25/2023 Corrections Issued RAUL OLAGI
Final 1/25/2023 Corrections Issued RAUL OLAGI
Green Building Final 1/25/2023 Approved RAUL OLAGI
HVAC-Final 1/25/2023 Approved RAUL OLAGI
PLUMBING-Final 1/25/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved RAUL OLAGI
ELECTRICAL-Final 2/24/2023 Approved RAUL OLAGI
Final 2/24/2023 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 2/24/2023 Approved RAUL OLAGI
Smoke Detectors 2/24/2023 Approved RAUL OLAGI