8613 W WYNGATE ST 91040

Certificate Information: 8613 W WYNGATE ST 91040

Application / Permit
22014-20000-04770
Plan Check / Job No.
B22VN14425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan PROPOSED 458 SQFT GROUND FLOOR ADDITION TO EXISTING SINGLE FAMILY HOUSE AND REMODEL.
Permit Issued
Issued on 3/9/2023
Issuing Office
Current Status
CofO Issued on 12/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 JAD BASMA
Corrections Issued 10/9/2022 JAD BASMA
Quality Review Completed 10/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/26/2023 JAD BASMA
Applicant returned to address corrections 3/1/2023 JAD BASMA
Plan Check Approved 3/9/2023 JAD BASMA
Issued 3/9/2023 APPLICANT
CofO in Progress 10/25/2023 DAVID ANDERSON
Permit Finaled 12/12/2023 RUBEN SALAS
CofO Issued 12/12/2023 RUBEN SALAS
Permit Finaled 12/12/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/14/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 12/14/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 1/22/2023 MATTHEW CRAIG
Grading Pre-Inspection Cleared 2/1/2023 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 3/6/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/19/2023 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 5/31/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 6/1/2023 Off-Hour Fees Due
Insulation 6/8/2023 Partial Approval DAVID ANDERSON
Wood Frame 6/8/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval DAVID ANDERSON
Deputy Wood Construction 6/22/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Approved DAVID ANDERSON
Gas Test 7/14/2023 Approved DAVID ANDERSON
HVAC-Rough 7/14/2023 Approved DAVID ANDERSON
PLUMBING-Rough 7/14/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 7/21/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 7/21/2023 Approved DAVID ANDERSON
Green Building Rough 7/21/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/21/2023 Approved DAVID ANDERSON
Insulation 7/26/2023 Approved DAVID ANDERSON
Drywall Nailing 8/25/2023 Approved DAVID ANDERSON
Shower Pan 8/25/2023 Approved DAVID ANDERSON
Final 10/23/2023 OK to Issue CofO DAVID ANDERSON
Footing/Foundation/Slab 10/23/2023 Approved DAVID ANDERSON
Green Building Final 10/23/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 10/23/2023 Approved DAVID ANDERSON