5318 N FELICE PL 91364
Certificate Information: 5318 N FELICE PL 91364
- Application / Permit
- 22014-20000-04755
- Plan Check / Job No.
- B22VN14397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADD 20'-3" X 9'-11" TO REAR OF EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; INTERIOR REMODEL
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | SELLA BENYAMIN |
| Corrections Issued | 10/26/2022 | SELLA BENYAMIN |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Applicant returned to address corrections | 11/14/2023 | SELLA BENYAMIN |
| Plan Check Approved | 12/20/2024 | SELLA BENYAMIN |
| No Progress | 12/26/2024 | SELLA BENYAMIN |
| Plan Check Approved | 12/26/2024 | SELLA BENYAMIN |
| Issued | 12/26/2024 | APPLICANT |
| CofO in Progress | 10/15/2025 | JOHN HAYES |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
| CofO Issued | 12/12/2025 | JOHN JANSON |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/20/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | RYAN KIM |
| Sewer availability | Cleared | 1/24/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Francisco Javier; Lic. No.: NA5126 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 5/8/2025 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 5/16/2025 | Approved | JOHN COLEMAN |
| Pre-Inspection | 5/27/2025 | Approved | JOHN HAYES |
| Deputy Reinf. Concrete | 5/28/2025 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 7/14/2025 | Corrections Issued | SCOTT SOBEL |
| Green Building Rough | 7/14/2025 | Partial Approval | SCOTT SOBEL |
| HVAC-Rough | 7/14/2025 | Approved | SCOTT SOBEL |
| PLUMBING-Rough | 7/14/2025 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Rough | 7/16/2025 | Approved | SCOTT SOBEL |
| Green Building Rough | 7/16/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | SCOTT SOBEL |
| Shower Pan | 7/16/2025 | Approved | SCOTT SOBEL |
| Insulation | 7/17/2025 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 7/21/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/21/2025 | Partial Approval | JOHN HAYES |
| Shower Pan | 7/21/2025 | Approved | JOHN HAYES |
| Drywall Nailing | 7/23/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JOHN HAYES |
| Final | 10/9/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/9/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 10/9/2025 | Approved | JOHN HAYES |
| Final | 10/15/2025 | OK to Issue CofO | JOHN HAYES |