1607 1/2 W FAIR PARK AVE 90041

Certificate Information: 1607 1/2 W FAIR PARK AVE 90041

Application / Permit
22014-20000-04729
Plan Check / Job No.
B22VN14308
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addtion to existing garage and covert garage into one story detached Accessory dwelling Unit per LAMC 12.22 A.33(c) and (d),
Permit Issued
Issued on 12/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/26/2022 RAMA DABADGE
Corrections Issued 9/26/2022 RAMA DABADGE
Building Plans Picked Up 10/4/2022 APPLICANT
Plan Check Approved 11/10/2022 MOHAMMAD ESMAILI
Issued 12/23/2022 APPLICANT
CofO in Progress 4/25/2025 DAVID WILLIAMS
Permit Finaled 4/26/2025 DEROLD HAUFF
CofO Issued 4/26/2025 DEROLD HAUFF
Permit Finaled 4/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/14/2022 VASIL MIHALEV
Address approval Cleared 10/31/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 10/31/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/1/2022 WALLIE JONG
Sewer availability Cleared 11/1/2022 WALLIE JONG
Tenant Habitability Plan Cleared 11/1/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Perez,, Manuel; Lic. No.: C73786 20850 SORRENTO LN      PORTER RANCH, CA 91326

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/1/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 9/1/2023 Approved CRAIG VAUGHAN
Underground Mechanical 9/1/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 9/13/2023 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/13/2023 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/15/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/22/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/22/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 11/22/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/22/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/22/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/6/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 12/6/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved CRAIG VAUGHAN
HVAC-Rough 12/6/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 12/6/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/20/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 12/20/2023 Approved ROY SPAULDING
Insulation 1/19/2024 Approved CRAIG VAUGHAN
Drywall Nailing 2/2/2024 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 2/2/2024 Approved JOAQUIN GREENOUGH
Final 1/2/2025 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 1/2/2025 Approved BRENDAN MORELLI
Green Building Final 1/2/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 1/2/2025 Approved BRENDAN MORELLI
Final 2/11/2025 Corrections Issued BRENDAN MORELLI
Gas Test 2/11/2025 Approved BRENDAN MORELLI
Green Building Final 2/11/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved BRENDAN MORELLI
Final 4/15/2025 Corrections Issued DAVID WILLIAMS
Final 4/25/2025 OK to Issue CofO DAVID WILLIAMS