11140 N TELFAIR AVE 91331
Certificate Information: 11140 N TELFAIR AVE 91331
- Application / Permit
- 22014-20000-04701
- Plan Check / Job No.
- B22VN14253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT & ADD 2-STORY 2-BEDROOMS, 2-BATHROOMS, LIVING, DINING ROOM & LAUNDRY ROOM (OVERALL DIMENSIONS IRR 32'-6" X 19'-9", 1095SF) PER LAMC 12.22A33(c)(d) **** SEE COMMENTS ****
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Valley
- Current Status
- Issued on 3/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/27/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/29/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/30/2022 | APPLICANT |
| Applicant returned to address corrections | 11/17/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/12/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/29/2022 | NILOOFAR MEHRAIN |
| Issued | 3/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 10/18/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/28/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 11/14/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/5/2026 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 4/16/2026 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 4/20/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/23/2026 | Approved | MISAEL ESPARZA |
| METHANE-Barrier | 4/23/2026 | Approved | MISAEL ESPARZA |
| METHANE-Subgrade | 4/23/2026 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2026 | Partial Approval | MICHEL ABAJAN |