10401-10403 N MEMORY PARK AVE 91345

Certificate Information: 10401-10403 N MEMORY PARK AVE 91345

Application / Permit
22014-20000-04634
Plan Check / Job No.
B22VN14031
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT, PER LAMC 12.22 A.33(c) and (e), AND 5'-6" X 19'-6" ADDITION TO THE ADU.
Permit Issued
Issued on 10/21/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 ARTIN ZARUKIAN
Corrections Issued 9/20/2022 ARTIN ZARUKIAN
Building Plans Picked Up 9/27/2022 APPLICANT
Plan Check Approved 10/21/2022 LUIS RINCON
Issued 10/21/2022 APPLICANT
CofO in Progress 4/20/2023 JENNIFER RABUCHIN
CofO Issued 5/8/2023 MICHAEL SMITH
Permit Finaled 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/12/2022 LUCIA MERCADO
Roof/Waste drainage to street Cleared 10/12/2022 LUCIA MERCADO
Eng Process Fee Ord 176,300 Cleared 10/20/2022 LUCIA MERCADO
Sewer availability Cleared 10/20/2022 LUCIA MERCADO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2022 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/1/2022 Partial Approval JENNIFER RABUCHIN
Sewer 12/1/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/12/2022 Partial Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/16/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/21/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/6/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 2/6/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Approved JENNIFER RABUCHIN
Gas Test 2/6/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 2/6/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 2/6/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/6/2023 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 2/6/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/8/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/8/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/8/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 2/10/2023 Approved JENNIFER RABUCHIN
Shower Pan 2/10/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/16/2023 Approved ROBERT GOLD
Green Building Rough 2/16/2023 Approved ROBERT GOLD
Insulation 2/16/2023 Approved ROBERT GOLD
Drywall Nailing 2/24/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/24/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/12/2023 Corrections Issued JENNIFER RABUCHIN
Final 4/12/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/12/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/12/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/12/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 4/12/2023 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 4/12/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/19/2023 Approved JENNIFER RABUCHIN
Final 4/19/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/19/2023 Approved JENNIFER RABUCHIN
Service/Power Release 4/19/2023 Approved JENNIFER RABUCHIN