10401-10403 N MEMORY PARK AVE 91345
Certificate Information: 10401-10403 N MEMORY PARK AVE 91345
- Application / Permit
- 22014-20000-04634
- Plan Check / Job No.
- B22VN14031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT, PER LAMC 12.22 A.33(c) and (e), AND 5'-6" X 19'-6" ADDITION TO THE ADU.
- Permit Issued
- Issued on 10/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 9/20/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| Plan Check Approved | 10/21/2022 | LUIS RINCON |
| Issued | 10/21/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | JENNIFER RABUCHIN |
| CofO Issued | 5/8/2023 | MICHAEL SMITH |
| Permit Finaled | 5/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | LUCIA MERCADO |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | LUCIA MERCADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | LUCIA MERCADO |
| Sewer availability | Cleared | 10/20/2022 | LUCIA MERCADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2022 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/1/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 12/1/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/12/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/16/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/21/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/6/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 2/6/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/6/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 2/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 2/6/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/8/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/8/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 2/10/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 2/10/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/16/2023 | Approved | ROBERT GOLD |
| Green Building Rough | 2/16/2023 | Approved | ROBERT GOLD |
| Insulation | 2/16/2023 | Approved | ROBERT GOLD |
| Drywall Nailing | 2/24/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/24/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/12/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/12/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/12/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/12/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/12/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/12/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 4/12/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| Final | 4/19/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/19/2023 | Approved | JENNIFER RABUCHIN |