4950 E ALDAMA ST 90042

Certificate Information: 4950 E ALDAMA ST 90042

Application / Permit
22014-20000-04633
Plan Check / Job No.
B22VN14025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16' X 11' 3" REAR BEDROOM ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
CofO Issued on 1/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/20/2022 GURUNATH NESARAJAH
Corrections Issued 9/20/2022 GURUNATH NESARAJAH
Building Plans Picked Up 9/22/2022 APPLICANT
Applicant returned to address corrections 1/19/2023 RAMA DABADGE
Applicant returned to address corrections 5/15/2023 GURUNATH NESARAJAH
Issued 5/25/2023 APPLICANT
CofO in Progress 1/23/2024 OSVALDO PARAMO
CofO in Progress 1/23/2024 OSVALDO PARAMO
CofO Issued 1/26/2024 DEROLD HAUFF
Permit Finaled 1/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/14/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 10/14/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 10/15/2022 CHRISTOPHER ROCHA
Specific Plan Cleared 11/7/2022 PABLO ESTRADA
Grading Pre-Inspection Cleared 1/9/2023 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2023 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 6/22/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/22/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 7/25/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Conditional Approval BRENDAN MORELLI
Wood Frame 7/25/2023 Conditional Approval BRENDAN MORELLI
Insulation 8/16/2023 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 8/16/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 8/22/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Approved OSVALDO PARAMO
Green Building Rough 8/22/2023 Approved OSVALDO PARAMO
Insulation 8/22/2023 Approved OSVALDO PARAMO
Drywall Nailing 8/28/2023 Approved JOSH MEISTER
Final 9/25/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 9/25/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 9/25/2023 Approved OSVALDO PARAMO
Final 9/27/2023 OK to Issue CofO OSVALDO PARAMO