305-305 1/2 E 56TH ST 90011

Certificate Information: 305-305 1/2 E 56TH ST 90011

Application / Permit
22014-20000-04613
Plan Check / Job No.
B22VN13964
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN EXISTING GARAGE/STORAGE TO BE CONVERTED TO ADU (499 SQ. FT.) PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 8/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 DANIEL SANJUAN
Corrections Issued 9/23/2022 DANIEL SANJUAN
Plan Check Approved 11/2/2022 KHUONG TRUONG
Issued 2/28/2023 APPLICANT
CofO in Progress 8/23/2023 ALEJANDRO DE ARTOLA
Permit Finaled 8/28/2023 DEROLD HAUFF
CofO Issued 8/28/2023 DEROLD HAUFF
Permit Finaled 8/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2022 WALLIE JONG
Sewer availability Cleared 10/4/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/7/2022 WALLIE JONG
Community Plan Implem. Overlay Cleared 11/1/2022 HELEN JADALI

Contact Information

Contractor Ervin Construction; Lic. No.: 1057891-B       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/10/2023 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 3/16/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/8/2023 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 5/8/2023 Corrections Issued BRENDAN MORELLI
Green Building Rough 5/8/2023 Approved BRENDAN MORELLI
HVAC-Rough 5/8/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 5/8/2023 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 5/9/2023 Conditional Approval BRENDAN MORELLI
Insulation 5/9/2023 Conditional Approval BRENDAN MORELLI
Pre-Inspection 5/9/2023 Conditional Approval BRENDAN MORELLI
Drywall Nailing 6/2/2023 Approved BRENDAN MORELLI
Underground Mechanical 6/8/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 7/20/2023 No Access for Inspection BRENDAN MORELLI
HVAC-Final 7/20/2023 No Access for Inspection BRENDAN MORELLI
PLUMBING-Final 7/20/2023 No Access for Inspection BRENDAN MORELLI
Service/Power Release 7/20/2023 No Access for Inspection BRENDAN MORELLI
ELECTRICAL-Final 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/10/2023 Approved ALIZAH MAYAGOITIA
Final 8/10/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 8/10/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 8/10/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 8/10/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Not Required ALIZAH MAYAGOITIA
Smoke Detectors 8/10/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/22/2023 Approved ALEJANDRO DE ARTOLA
Final 8/22/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 8/22/2023 Approved ALEJANDRO DE ARTOLA